230-234 N BERENDO ST 90004
Certificate Information: 230-234 N BERENDO ST 90004
- Application / Permit
- 20016-10000-08924
- Plan Check / Job No.
- B20LA06403
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- REMODEL EXISTING APARTMENT INTERIOR MODIFICATION, RELOCATE KITCHENS. CONVERT (E) ATTACHED GARAGE TP ATTACHED ADU PER GCS 6582.2(e)(1)(C) for existing multifamily dwelling.
- Permit Issued
- Issued on 9/2/2020
- Issuing Office
- Current Status
- CofO Issued on 2/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 5/7/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 5/12/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 5/19/2020 | APPLICANT |
| Green Plans Picked Up | 6/23/2020 | APPLICANT |
| Applicant returned to address corrections | 8/5/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/19/2020 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 8/20/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/1/2020 | CRYSTEL MAALOUF |
| Issued | 9/2/2020 | APPLICANT |
| CofO in Progress | 2/1/2021 | ERNESTO CORRAL |
| CofO Issued | 2/1/2021 | ERNESTO CORRAL |
| Permit Finaled | 2/1/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/4/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | JEANIE LAM |
| Green Code | Cleared | 6/22/2020 | VIVIAN LAO |
Contact Information
| Contractor | Regreen Inc; Lic. No.: 939440-B | 120 STANDARD ST EL SEGUNDO, CA 90245 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/17/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Rough | 9/17/2020 | Not Ready for Inspection | ROBERT VORHIS |
| METHANE-Rough | 9/17/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Wood Frame | 9/17/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Final | 1/29/2021 | Conditional Approval | EDWIN GREGORYONA |
| Green Building Final | 1/29/2021 | Approved | EDWIN GREGORYONA |
| Green Building Rough | 1/29/2021 | Approved | EDWIN GREGORYONA |
| METHANE-Final | 1/29/2021 | Approved | EDWIN GREGORYONA |
| METHANE-Rough | 1/29/2021 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 1/29/2021 | Approved | EDWIN GREGORYONA |
| Wood Frame | 1/29/2021 | Approved | EDWIN GREGORYONA |
| Final | 2/1/2021 | OK to Issue CofO | ERNESTO CORRAL |