750 W BASIN ST 90731
Certificate Information: 750 W BASIN ST 90731
- Application / Permit
- 20016-10000-08913
- Plan Check / Job No.
- B20LA06378
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- CHANGE OF USE FOR PORTION OF THE EXISTING BAKERY WAREHOUSE TO CREATE 5200-SF OFFICE AREA, RE-STRIPE PARKING LOT, INSTALL 2 NEW ROOFTOP AC UNITS AND NEW ROOF ACCESS LADDER, REPLACING EXISTING EXTERIOR DOORS AND STAIRS WITH NEW AND NEW RAMP.
- Permit Issued
- Issued on 11/20/2020
- Issuing Office
- Current Status
- CofO Issued on 10/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | JOHNNY WU |
| Disabled Access Plans Picked Up | 4/28/2020 | APPLICANT |
| Corrections Issued | 4/29/2020 | JOHNNY WU |
| Quality Review Completed | 5/4/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 5/7/2020 | APPLICANT |
| Green Plans Picked Up | 7/15/2020 | APPLICANT |
| Applicant returned to address corrections | 7/16/2020 | JOHNNY WU |
| Plan Check Approved | 11/18/2020 | JOHNNY WU |
| Issued | 11/20/2020 | APPLICANT |
| CofO in Progress | 9/14/2023 | AMANUEL BERHE |
| Permit Finaled | 10/25/2023 | DAVID TSAU |
| CofO Issued | 10/25/2023 | DAVID TSAU |
| Permit Finaled | 10/25/2023 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 7/14/2020 | KHEDER ALRAZAA |
| Sewer availability | Cleared | 7/22/2020 | YEGANEH SADEGHI |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2020 | YEGANEH SADEGHI |
| DAS Clearance | Cleared | 8/27/2020 | JOHNNY WU |
| "D" conditions | Cleared | 10/21/2020 | JEANALEE OBERGFELL |
| ZI | Cleared | 10/21/2020 | JEANALEE OBERGFELL |
Contact Information
| Architect | Dimeglio,, Louis J; Lic. No.: C14257 | 115 ALHAMBRA IRVINE, CA 92620 |
| Contractor | Strategic Service Solutions Inc; Lic. No.: 988772-B | 999 CORPORATE DR STE 100 LADERA RANCH, CA 92694 |
| Engineer | Lascola,, James Joseph; Lic. No.: S3149 | 26652 VUELTA RICA CAPISTRANO, CA 92624 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 10/19/2021 | Partial Approval | JOEY BUCHANAN |
| Insulation | 3/2/2022 | No Access for Inspection | JOEY BUCHANAN |
| Insulation | 3/31/2022 | Approved | JOEY BUCHANAN |
| Light Gage Steel Frame | 4/4/2022 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 4/25/2022 | Approved | JOEY BUCHANAN |
| Final | 8/25/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Green Building Final | 8/25/2023 | Approved | AMANUEL BERHE |
| Green Building Rough | 8/25/2023 | Approved | AMANUEL BERHE |
| METHANE-Final | 8/25/2023 | Approved | AMANUEL BERHE |
| METHANE-Rough | 8/25/2023 | Approved | AMANUEL BERHE |
| Reinforced Masonry Frame | 8/25/2023 | Approved | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Not Ready | AMANUEL BERHE |
| Smoke Detectors | 8/25/2023 | Approved | AMANUEL BERHE |
| Final | 9/1/2023 | Not Ready for Inspection | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | AMANUEL BERHE |
| Final | 9/6/2023 | Not Ready for Inspection | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV No Gas | AMANUEL BERHE |
| Final | 9/11/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Final | 9/13/2023 | OK to Issue CofO | AMANUEL BERHE |