4950 W SUNSET BLVD 3RD-4TH FLOOR 90027
Certificate Information: 4950 W SUNSET BLVD 3RD-4TH FLOOR 90027
- Application / Permit
- 20016-10000-08825
- Plan Check / Job No.
- B20LA06287
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- Tenant improvement on mezzanine, level 3, and 4 (approximately 16714 SF), and demolition (of existing storage, staff lounge, and offices) and buildout of offices on level 3 (approximately 1231 SF) in existing Medical Office Building. No change in use of building/ occupancy type, structure, exterior work, and parking.
- Permit Issued
- Issued on 7/24/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/16/2020
Permit Application Status History
| Submitted | 4/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | DEAN LEE |
| Corrections Issued | 4/21/2020 | DEAN LEE |
| Quality Review Completed | 4/27/2020 | BILL STUTSMAN |
| Disabled Access Plans Picked Up | 4/29/2020 | APPLICANT |
| Green Plans Picked Up | 5/1/2020 | APPLICANT |
| Applicant returned to address corrections | 5/19/2020 | DEAN LEE |
| Plan Check Approved | 7/24/2020 | STARR CHEN |
| Issued | 7/24/2020 | APPLICANT |
| Permit Finaled | 11/16/2020 | EDWIN GREGORYONA |
Permit Application Clearance Information
| ZA Case | Cleared | 5/19/2020 | KENTON TRINH |
| Specific Plan | Cleared | 5/27/2020 | JASON HERNANDEZ |
| Green Code | Cleared | 6/10/2020 | VIVIAN LAO |
| ZI | Cleared | 6/17/2020 | KENTON TRINH |
| DAS Clearance | Cleared | 7/9/2020 | DEAN LEE |
Contact Information
| Architect | Lee,, Loretta J; Lic. No.: C33899 | 5955 W 8TH STREET UNIT 107 LOS ANGELES, CA 90036 |
| Contractor | Kaiser Foundation Health Plan Inc; Lic. No.: 370871-B | 4175 E LA PALMA AVE STE 200 ANAHEIM, CA 92807 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/28/2020 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 7/28/2020 | Approved | EDWIN GREGORYONA |
| Final | 11/16/2020 | Permit Finaled | EDWIN GREGORYONA |
| Green Building Final | 11/16/2020 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 11/16/2020 | Approved | EDWIN GREGORYONA |