11842 W RIALTO ST 91352

Certificate Information: 11842 W RIALTO ST 91352

Application / Permit
20016-10000-08806
Plan Check / Job No.
B20LA06263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert existing 1st floor 3-car garage and second dwelling unit on 2nd floor to Accessory Dwelling Unit per Ordinance
Permit Issued
Issued on 6/2/2020
Issuing Office
Current Status
CofO Issued on 2/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 VU NGUYEN
Corrections Issued 4/22/2020 VU NGUYEN
Quality Review Completed 4/24/2020 TU HUA
Applicant returned to address corrections 5/11/2020 VU NGUYEN
Applicant returned to address corrections 5/12/2020 VU NGUYEN
Plan Check Approved 6/2/2020 VU NGUYEN
Issued 6/2/2020 APPLICANT
CofO in Progress 11/16/2020 JOHN HAYES
Permit Finaled 2/19/2021 MICHAEL SMITH
CofO Issued 2/19/2021 MICHAEL SMITH
Permit Finaled 2/19/2021 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/4/2020 Not Ready for Inspection PIERRE VEGA
Excavation/Setback/Form/Re-Bar 8/4/2020 Corrections Issued PIERRE VEGA
PLUMBING-Rough 8/4/2020 Not Ready for Inspection PIERRE VEGA
Wood Frame 8/4/2020 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 8/7/2020 Not Ready for Inspection BEAU COLLINS
Footing/Foundation/Slab 8/7/2020 Partial Approval BEAU COLLINS
PLUMBING-Rough 8/7/2020 Corrections Issued BEAU COLLINS
Wood Frame 8/7/2020 Not Ready for Inspection BEAU COLLINS
Footing/Foundation/Slab 8/11/2020 Approved MATTHEW NELSON
Rough-Elec/Plmb/HVAC 8/11/2020 Not Ready for Inspection MATTHEW NELSON
Wood Frame 8/11/2020 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 8/26/2020 Approved MATTHEW NELSON
HVAC-Rough 8/26/2020 Approved MATTHEW NELSON
Drywall Nailing 9/1/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 9/1/2020 Corrections Issued BEAU COLLINS
Drywall Nailing 9/2/2020 Approved MATTHEW NELSON
Insulation 9/2/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/2/2020 Approved MATTHEW NELSON
Shower Pan 9/15/2020 Approved DAVID MATSON
BUILDING-Rough-Frame 10/23/2020 Not Ready for Inspection JOHN HAYES
Final 10/23/2020 Corrections Issued JOHN HAYES
Green Building Final 10/23/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/23/2020 Not Ready for Inspection JOHN HAYES
MERV13>=Final 10/23/2020 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 10/23/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 10/23/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/4/2020 Not Ready for Inspection JOHN HAYES
Final 11/4/2020 Corrections Issued JOHN HAYES
Green Building Final 11/4/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 11/4/2020 Not Ready for Inspection JOHN HAYES
MERV13>=Final 11/4/2020 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 11/4/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 11/4/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 11/4/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/13/2020 Approved JOHN HAYES
ELECTRICAL-Final 11/13/2020 Approved JOHN HAYES
Final 11/13/2020 OK to Issue CofO JOHN HAYES
Green Building Final 11/13/2020 Approved JOHN HAYES
Green Building Rough 11/13/2020 Approved JOHN HAYES
HVAC-Final 11/13/2020 Approved JOHN HAYES
MERV13>=Final 11/13/2020 Approved JOHN HAYES
MERV13>=Rough 11/13/2020 Approved JOHN HAYES
PLUMBING-Final 11/13/2020 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 11/13/2020 SGSOV Approved JOHN HAYES
Smoke Detectors 11/13/2020 Approved JOHN HAYES