8631 W 3RD ST SUITE#815 90048
Certificate Information: 8631 W 3RD ST SUITE#815 90048
- Application / Permit
- 20016-10000-08776
- Plan Check / Job No.
- B20LA06222
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- TENANT IMPROVEMENTS FOR (E) MEDICAL OFFICE SUITE 815 WITHIN EXISTING EAST TOWER BUILDING, REPLACE DOOR IN CORRIDOR. ALL DEMOLITION IS NON-LOAD BEARING & IS LOCATED ON THE EIGTH FLOOR. AREA OF WORK = 3,049 S.F.
- Permit Issued
- Issued on 8/31/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/10/2020
Permit Application Status History
| Submitted | 4/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | JOHNNY WU |
| Corrections Issued | 5/11/2020 | JOHNNY WU |
| Quality Review Completed | 5/12/2020 | LAWRENCE QUIRANTE |
| Disabled Access Plans Picked Up | 5/18/2020 | APPLICANT |
| Green Plans Picked Up | 7/29/2020 | APPLICANT |
| Applicant returned to address corrections | 8/5/2020 | JOHNNY WU |
| Plan Check Approved | 8/31/2020 | JOHNNY WU |
| Issued | 8/31/2020 | APPLICANT |
| Permit Finaled | 11/9/2020 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Green Code | Cleared | 7/23/2020 | VIVIAN LAO |
| Sewer availability | Cleared | 7/23/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2020 | ELENA LOPEZ |
| DAS Clearance | Cleared | 8/18/2020 | EDDIE GARIN |
| Fire Marshall Fire Life Safety | Cleared | 8/24/2020 | MENOA AGHAJANI |
Contact Information
| Architect | Clinger,, Daniel H; Lic. No.: C11325 | CSA ARCHITECTS 21021 VENTURA BLVD STE 330 WOODLAND HILLS, CA 91364 |
| Contractor | Warner Constructors Inc; Lic. No.: 463497-B | 6333 SAN FERNANDO ROAD GLENDALE, CA 91201 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 9/9/2020 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 9/9/2020 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 9/16/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 9/18/2020 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 10/19/2020 | Approved | TIMOTHY BUXTON |
| Final | 11/9/2020 | Permit Finaled | RUSSELL BONVOULOIR |
| Green Building Final | 11/9/2020 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 11/9/2020 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 11/9/2020 | Approved | RUSSELL BONVOULOIR |