3823 S HEPBURN AVE 90008
Certificate Information: 3823 S HEPBURN AVE 90008
- Application / Permit
- 20016-10000-08757
- Plan Check / Job No.
- B20LA06195
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 1/21/2021
- Issuing Office
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2020 | APPLICANT |
| No Progress | 4/20/2020 | GEORGE ALVAREZ |
| Assigned to Plan Check Engineer | 4/20/2020 | GEORGE ALVAREZ |
| Corrections Issued | 4/20/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 12/22/2020 | FERNANDO FLORES |
| Plan Check Approved | 1/6/2021 | SINA KHOSRAVI |
| Issued | 1/21/2021 | APPLICANT |
| Building Plans Picked Up | 1/27/2021 | APPLICANT |
| CofO in Progress | 12/19/2023 | ANTHONY EGSON |
| CofO Issued | 12/22/2023 | DEROLD HAUFF |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/20/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/20/2020 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/8/2020 | JEANIE LAM |
| Sewer availability | Cleared | 12/8/2020 | JEANIE LAM |
| Address approval | Cleared | 12/9/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2020 | JEANIE LAM |
Contact Information
| Architect | Francis,, Christopher David; Lic. No.: C19015 | 37370 HARVEST DR. MURRIETA, CA 92563 |
| Contractor | National Construction & Development Inc; Lic. No.: 702019-B | PO BOX 867 WOODLAND HILLS, CA 91365 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/17/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 2/19/2021 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 2/24/2021 | Approved | DAVID FEILER |
| Sewer | 2/24/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 3/25/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 6/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/23/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/29/2021 | Approved | ALFREDO BALANDRA |
| PLUMBING-Rough | 6/29/2021 | Conditional Approval | ALFREDO BALANDRA |
| BUILDING-Rough-Frame | 7/13/2021 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 11/12/2021 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/12/2021 | Approved | ANTHONY EGSON |
| HVAC-Rough | 11/12/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 11/12/2021 | Conditional Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/1/2021 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/1/2021 | Approved | ANTHONY EGSON |
| HVAC-Rough | 12/1/2021 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/10/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 1/18/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/18/2022 | Approved | ANTHONY EGSON |
| Insulation | 2/14/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/22/2022 | Approved | HORACE FULTZ |
| Drywall Nailing | 3/3/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 3/3/2022 | Partial Approval | HORACE FULTZ |
| ELECTRICAL-Final | 6/22/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 6/22/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 6/22/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 6/22/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 8/17/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 8/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 8/31/2023 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 8/31/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 9/20/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 9/20/2023 | Approved | ANTHONY EGSON |
| Final | 11/7/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 12/19/2023 | OK to Issue CofO | ANTHONY EGSON |