1200 S FIGUEROA ST 90015

Certificate Information: 1200 S FIGUEROA ST 90015

Application / Permit
20016-10000-08736
Plan Check / Job No.
B20LA06169
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
CHANGE OF USE FROM RETAIL TO BANK (6034 SQ.FT.), AND TENANT IMPROVEMENT. (CORE AND SHELL PERMIT 13010-10000-04232)
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
CofO Issued on 1/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 JOHNNY WU
Disabled Access Plans Picked Up 4/23/2020 APPLICANT
Corrections Issued 5/1/2020 JOHNNY WU
Quality Review Completed 5/4/2020 LAWRENCE QUIRANTE
Building Plans Picked Up 5/8/2020 APPLICANT
Applicant returned to address corrections 7/16/2020 JOHNNY WU
Green Plans Picked Up 7/20/2020 APPLICANT
Plan Check Approved 9/24/2020 JOHNNY WU
Issued 9/24/2020 APPLICANT
CofO in Progress 1/18/2022 TIMOTHY BUXTON
CofO Issued 1/18/2022 TED RIES
Permit Finaled 1/18/2022 TED RIES

Permit Application Clearance Information

APC Cleared 5/19/2020 DANIEL CORONADO
CPC Cleared 5/19/2020 DANIEL CORONADO
CPC Cleared 5/19/2020 DANIEL CORONADO
CPC Cleared 5/19/2020 DANIEL CORONADO
CPC Cleared 5/19/2020 DANIEL CORONADO
CPC Cleared 5/19/2020 DANIEL CORONADO
CPC Cleared 5/19/2020 DANIEL CORONADO
CPC Cleared 5/19/2020 DANIEL CORONADO
CPC Cleared 5/19/2020 DANIEL CORONADO
Comm Cor/Mini-Mall Cleared 5/19/2020 DANIEL CORONADO
ZA Case Cleared 5/19/2020 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 5/20/2020 RENZ SORIANO
Historic Resource Verification Cleared 5/20/2020 MICAELA TORRES-GIL
Sewer availability Cleared 5/21/2020 RENZ SORIANO
Specific Plan Cleared 6/3/2020 PETE EYRE
Specific Plan Cleared 7/1/2020 MAIRA SANCHEZ
DAS Clearance Cleared 7/9/2020 JOHNNY WU
Green Code Cleared 7/20/2020 VIVIAN LAO
Redevelopment Project Area Cleared 9/14/2020 DAVID URITA

Contact Information

Architect Reno,, Brian N; Lic. No.: C29831 301 DEVONSHIRE ROAD      TOWER LAKES, IL 60010
Contractor T Morrissey Corporation; Lic. No.: 708936-B 3740 OCEANIC WAY SUITE 301      OCEANSIDE, CA 92056
Engineer Mirahsani,, Ramin; Lic. No.: S6327 10500 NE 8TH ST STE 800      BELLEVUE, WA 98004

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 1/13/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/13/2021 Partial Approval DANIEL COLLINS
Pre-Inspection 1/13/2021 Approved DANIEL COLLINS
Footing/Foundation/Slab 1/25/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/17/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/5/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 4/5/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 6/2/2021 Partial Approval DANIEL COLLINS
Structural Steel Frame 6/2/2021 Partial Inspection DANIEL COLLINS
Green Building Rough 7/15/2021 Approved DANIEL COLLINS
METHANE-Rough 7/15/2021 Approved DANIEL COLLINS
Reinforced Concrete Frame 7/15/2021 Approved DANIEL COLLINS
T-Bar Ceiling 7/15/2021 Conditional Approval DANIEL COLLINS
Pre-Inspection 8/18/2021 Approved TIMOTHY BUXTON
Pre-Inspection 8/27/2021 Approved TIMOTHY BUXTON
Pre-Inspection 8/30/2021 Partial Inspection DANIEL COLLINS
Deputy Drilled-In Anchors 9/1/2021 Conditional Approval TIMOTHY BUXTON
Final 9/16/2021 Not Ready for Inspection TIMOTHY BUXTON
Green Building Final 9/16/2021 Not Ready for Inspection TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV No Gas TIMOTHY BUXTON
Smoke Detectors 9/16/2021 Approved TIMOTHY BUXTON
Deputy Wood Construction 9/27/2021 Conditional Approval TIMOTHY BUXTON
Final 9/28/2021 Conditional Approval TIMOTHY BUXTON
Green Building Final 9/28/2021 Approved TIMOTHY BUXTON