601 N NIMES ROAD 90077
Certificate Information: 601 N NIMES ROAD 90077
- Application / Permit
- 20016-10000-08728
- Plan Check / Job No.
- B20LA06157
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ACCESSORY BUILDING TO A SINGLE FAMILY HOME AND MINOR REMODEL PER PARCEL MAP UNDER AA-2018-406-PMLA
- Permit Issued
- Issued on 3/24/2023
- Issuing Office
- Current Status
- Issued on 3/24/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 4/21/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/27/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 5/4/2020 | APPLICANT |
| Applicant returned to address corrections | 7/13/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 9/27/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/11/2023 | ARSALAN SHABESTARI |
| Issued | 3/24/2023 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/29/2020 | GEORGE SUCHAND |
| Address approval | Cleared | 5/6/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/6/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/6/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/6/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2020 | DINAH GARIN |
| Tract Map conditions | Cleared | 5/15/2020 | MAXFIELD VERMY |
| Tract Map conditions | Cleared | 5/15/2020 | MAXFIELD VERMY |
| Tract Map conditions | Cleared | 5/15/2020 | MAXFIELD VERMY |
| Tract Map conditions | Cleared | 5/15/2020 | MAXFIELD VERMY |
| Tract Map conditions | Cleared | 5/15/2020 | MAXFIELD VERMY |
| Tract Map conditions | Cleared | 5/15/2020 | MAXFIELD VERMY |
| Tract Map conditions | Cleared | 5/15/2020 | MAXFIELD VERMY |
| ZI | Cleared | 5/15/2020 | MAXFIELD VERMY |
| ZI | Cleared | 5/15/2020 | MAXFIELD VERMY |
| Sewer availability | Cleared | 8/7/2020 | DINAH GARIN |
| Tract Map conditions | Cleared | 12/28/2022 | MAXFIELD VERMY |
Contact Information
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | 5168 W PICO BLVD LOS ANGELES, CA 90019 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/12/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 5/12/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 5/12/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 5/12/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 5/19/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/19/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 5/19/2023 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 5/26/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 5/26/2023 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/26/2023 | Approved | CHRISTOPHER WILSON |
| Insulation | 5/26/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 10/5/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 10/5/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Shower Pan | 10/5/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 10/5/2023 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 10/20/2023 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 10/20/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 10/20/2023 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 11/3/2023 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 11/3/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Shower Pan | 11/3/2023 | Approved | CHRISTOPHER WILSON |
| Special/Order Compliance | 11/3/2023 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/17/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 1/17/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Insulation | 1/17/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/19/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 3/19/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Rough | 3/19/2024 | Approved | CHRISTOPHER WILSON |
| Insulation | 3/19/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 3/19/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 3/19/2024 | Partial Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 4/5/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/12/2024 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 7/18/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 7/18/2024 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 7/18/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Service/Power Release | 7/18/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 7/18/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |