1600 N CAMPUS ROAD 90032

Certificate Information: 1600 N CAMPUS ROAD 90032

Application / Permit
20016-10000-08726
Plan Check / Job No.
B20LA06156
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) College
Work Description
Alteration of existing arcade structure surrounding existing pool. removal of non-original roof and colonnade to restore original facade. construction of new staircase to existing running track. removal of existing stairs into existing building and interior tenant improvements
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
Permit Finaled on 11/30/2022

Permit Application Status History

Submitted 4/27/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 SERGIO GUTIERREZ
Disabled Access Plans Picked Up 5/26/2020 APPLICANT
Corrections Issued 5/29/2020 SERGIO GUTIERREZ
Quality Review Completed 6/18/2020 KESETE HAREGOT
Building Plans Picked Up 6/22/2020 APPLICANT
Applicant returned to address corrections 4/20/2021 SERGIO GUTIERREZ
Green Plans Picked Up 7/8/2021 APPLICANT
Applicant returned to address corrections 7/26/2021 SERGIO GUTIERREZ
Plan Check Approved 8/13/2021 SERGIO GUTIERREZ
Issued 9/9/2021 APPLICANT
Permit Finaled 11/29/2022 MARK FERRARI

Permit Application Clearance Information

Green Code Cleared 3/31/2021 AARON COSTA
CPC Cleared 5/21/2021 RUBEN VASQUEZ
CPC Cleared 5/21/2021 RUBEN VASQUEZ
CPC Cleared 5/21/2021 RUBEN VASQUEZ
ZA Case Cleared 5/21/2021 RUBEN VASQUEZ
DAS Clearance Cleared 6/30/2021 EDDIE GARIN
DAS Clearance Cleared 6/30/2021 SERGIO GUTIERREZ
Low Impact Development Cleared 7/29/2021 ANDRES COVARRUBIAS
Grading Pre-Inspection Cleared 8/13/2021 SERGIO GUTIERREZ

Contact Information

Contractor Tovey / Shultz Construction Inc; Lic. No.: 549838-B 18261 COLLIER AVE UNIT A      LAKE ELSINORE, CA 92530
Engineer Breaks,, Matthew Calvin; Lic. No.: S6028 5056 TUJUNGA AVE APT 17      NORTH HOLLYWOOD, CA 91601

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 10/15/2021 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 11/9/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 11/9/2021 Conditional Approval MARK FERRARI
Wood Frame 12/10/2021 Partial Approval MARK FERRARI
Footing/Foundation/Slab 3/9/2022 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 3/10/2022 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 3/14/2022 Conditional Approval MARK FERRARI
Wood Frame 3/18/2022 Partial Approval MARK FERRARI
Wood Frame 3/23/2022 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 4/28/2022 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 4/28/2022 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 5/5/2022 Conditional Approval MARK FERRARI
Light Gage Steel Frame 5/13/2022 Partial Approval MARK FERRARI
Drywall Nailing 5/20/2022 Approved MARK FERRARI
Interior/Exterior Lathing 7/13/2022 Approved MARK FERRARI
Final 11/29/2022 Permit Finaled MARK FERRARI
Green Building Final 11/29/2022 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Approved MARK FERRARI
Smoke Detectors 11/29/2022 Approved MARK FERRARI