7325 W 85TH ST 90045

Certificate Information: 7325 W 85TH ST 90045

Application / Permit
20016-10000-08655
Plan Check / Job No.
B20LA06092
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. ADU Conversion. Existing garage to be converted into Accessory dwelling unit per state law LAMC 12.22A.33(B)(5)
Permit Issued
Issued on 8/6/2020
Issuing Office
Current Status
CofO Issued on 12/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 MONICA RAMIREZ
Corrections Issued 4/7/2020 MONICA RAMIREZ
Quality Review Completed 4/14/2020 TU HUA
Applicant returned to address corrections 5/27/2020 MONICA RAMIREZ
Applicant returned to address corrections 7/6/2020 MONICA RAMIREZ
Plan Check Approved 7/29/2020 MONICA RAMIREZ
Issued 8/6/2020 APPLICANT
CofO in Progress 11/30/2021 RICHARD STEINBACH
Permit Finaled 12/3/2021 DANIEL ORRANTE
CofO Issued 12/3/2021 DANIEL ORRANTE
Permit Finaled 12/3/2021 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/8/2020 DINAH GARIN
Sewer availability Cleared 5/8/2020 DINAH GARIN
Construction near power lines Cleared 5/11/2020 RIDWAN HARDY
Construction within easement Cleared 5/11/2020 RIDWAN HARDY
Specific Plan Cleared 5/14/2020 SHEILA GERSHON
Grading Pre-Inspection Cleared 5/21/2020 BRIAN MILLER
Address approval Cleared 7/16/2020 DINAH GARIN

Contact Information

Contractor Tega Builders Inc; Lic. No.: 1041646-B 5656 WISH AV      ENCINO, CA 91316

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/25/2020 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/26/2020 Partial Approval KENNETH NAGLE
PLUMBING-Rough 8/26/2020 Partial Approval KENNETH NAGLE
Sewer 8/26/2020 Approved KENNETH NAGLE
ELECTRICAL-Rough 9/15/2020 Approved JUAN VALENZUELA
PLUMBING-Rough 9/15/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Partial Approval JUAN VALENZUELA
Insulation 10/13/2020 Partial Inspection JUAN VALENZUELA
METHANE-Rough 10/13/2020 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 10/20/2020 Conditional Approval JUAN VALENZUELA
HVAC-Rough 10/20/2020 Approved JUAN VALENZUELA
Insulation 10/20/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 10/20/2020 Approved JUAN VALENZUELA
Drywall Nailing 11/4/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 3/15/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 3/15/2021 Approved JUAN VALENZUELA
Final 3/15/2021 Corrections Issued JUAN VALENZUELA
HVAC-Final 3/15/2021 Approved JUAN VALENZUELA
METHANE-Final 3/15/2021 Approved JUAN VALENZUELA
METHANE-Rough 3/15/2021 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 3/15/2021 Approved JUAN VALENZUELA
PLUMBING-Final 3/17/2021 Approved JUAN VALENZUELA
Final 11/30/2021 OK to Issue CofO RICHARD STEINBACH