4250 S NORTON AVE 90008
Certificate Information: 4250 S NORTON AVE 90008
- Application / Permit
- 20016-10000-08519
- Plan Check / Job No.
- B20LA05978
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 12/7/2021
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2020 | RACHEL BEYENE |
| Corrections Issued | 4/17/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 11/17/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 4/22/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 5/14/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 7/3/2021 | TSE MING HUANG |
| Plan Check Approved | 10/6/2021 | GEORGE ALVAREZ |
| Issued | 12/7/2021 | APPLICANT |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
| CofO in Progress | 2/19/2026 | LUIS CASTRO |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2020 | THOMAS LANG |
| Sewer availability | Cleared | 7/2/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/17/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 9/20/2024 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Conditional Approval | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 10/18/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/18/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/6/2024 | Corrections Issued | BARRY HACHE |
| Shower Pan | 11/6/2024 | Approved | BARRY HACHE |
| PLUMBING-Rough | 11/13/2024 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 12/9/2024 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 2/14/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 6/9/2025 | Approved | LUIS CASTRO |
| Special/Order Compliance | 6/9/2025 | Corrections Issued | LUIS CASTRO |
| Wood Frame | 6/9/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 6/20/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | LUIS CASTRO |
| Final | 2/9/2026 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 2/9/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 2/9/2026 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 2/18/2026 | Approved | LUIS CASTRO |
| Final | 2/18/2026 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 2/18/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 2/18/2026 | Approved | LUIS CASTRO |