1723 S BARRINGTON AVE 90025
Certificate Information: 1723 S BARRINGTON AVE 90025
- Application / Permit
- 20016-10000-08384
- Plan Check / Job No.
- B20LA05895
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH93 INSTALL 3 SPECIAL CANTILEVERED COLUMNS
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- CofC Issued on 1/28/2021
Permit Application Status History
| Submitted | 4/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2020 | JESSE VIDUYA |
| Corrections Issued | 4/30/2020 | JESSE VIDUYA |
| Quality Review Completed | 5/5/2020 | SAI KHUM |
| Building Plans Picked Up | 7/21/2020 | APPLICANT |
| Plan Check Approved | 9/3/2020 | JESSE VIDUYA |
| Issued | 10/20/2020 | APPLICANT |
| OK for CofC | 1/26/2021 | GRANT WOODS |
| CofC Issued | 1/28/2021 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/16/2020 | ISMAEL HERNANDEZ |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | 145 S FAIRFAX STE 200/300 LOS ANGELES, CA 90036 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/1/2020 | Approved | ALAN NOVAK |
| Wood Frame | 12/4/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 12/18/2020 | Approved | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 12/18/2020 | Approved | GRANT WOODS |
| Structural Steel Frame | 12/18/2020 | Approved | GRANT WOODS |
| Wood Frame | 12/21/2020 | Approved | JOHN DODGE |
| Deputy Reinf. Concrete | 12/22/2020 | Conditional Approval | JOHN DODGE |
| Interior/Exterior Lathing | 12/31/2020 | Approved | GRANT WOODS |
| Final | 1/21/2021 | Not Ready for Inspection | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 1/21/2021 | SGSOV Not Ready | JOHN DODGE |
| Smoke Detectors | 1/21/2021 | Not Ready for Inspection | JOHN DODGE |
| Final | 1/26/2021 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 1/26/2021 | Approved | GRANT WOODS |