422 S ARNAZ DR 90048
Certificate Information: 422 S ARNAZ DR 90048
- Application / Permit
- 20016-10000-08383
- Plan Check / Job No.
- B20LA05894
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 2534 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 1/21/2021
- Issuing Office
- Current Status
- CofC Issued on 5/5/2021
Permit Application Status History
| Submitted | 4/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | VARAND SARKISIAN |
| Corrections Issued | 5/14/2020 | VARAND SARKISIAN |
| Quality Review Completed | 5/20/2020 | SAI KHUM |
| Plan Check Approved | 8/5/2020 | VARAND SARKISIAN |
| Issued | 1/21/2021 | APPLICANT |
| OK for CofC | 5/5/2021 | MARK FERRARI |
| CofC Issued | 5/5/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/6/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/4/2021 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 2/16/2021 | Partial Inspection | JONATHAN QUACH |
| Structural Steel Frame | 2/16/2021 | Partial Inspection | JONATHAN QUACH |
| Wood Frame | 2/16/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 2/17/2021 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 2/17/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 2/17/2021 | Approved | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 2/18/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 2/18/2021 | Conditional Approval | JONATHAN QUACH |
| Interior/Exterior Lathing | 2/24/2021 | Approved | JONATHAN QUACH |
| Final | 3/31/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 3/31/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 3/31/2021 | Approved | DARRYL ARNOLD |
| Final | 5/5/2021 | OK for CofC | MARK FERRARI |