3450 W 6TH ST #105 90020
Certificate Information: 3450 W 6TH ST #105 90020
- Application / Permit
- 20016-10000-08341
- Plan Check / Job No.
- B20LA05874
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Chage of use from Retail to Restaurant (1509 sqft). >>>>>Hours of Operation from 7 a.m. to 11 p.m<<<<<
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Current Status
- CofO Issued on 12/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2020 | SALVADOR QUINTANILLA |
| Corrections Issued | 4/16/2020 | TSE MING HUANG |
| Disabled Access Plans Picked Up | 5/1/2020 | APPLICANT |
| Quality Review Completed | 5/13/2020 | KEN GILL |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| Applicant returned to address corrections | 4/19/2022 | TSE MING HUANG |
| Plan Check Approved | 6/8/2022 | SALVADOR QUINTANILLA |
| Issued | 6/10/2022 | APPLICANT |
| CofO in Progress | 12/5/2022 | KATY RAMIREZ |
| CofO Issued | 12/6/2022 | ERNESTO CORRAL |
| Permit Finaled | 12/6/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 5/17/2021 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 5/20/2021 | STEVE MELGAR |
| Redevelopment Project Area | Cleared | 6/2/2021 | GRACIELA ACOSTA |
| Food Service Establishment | Cleared | 6/15/2021 | JASH PATEL |
| DAS Clearance | Cleared | 5/18/2022 | EDDIE GARIN |
| ZA Case | Cleared | 5/23/2022 | JASON CHAN |
| Food establishment approval | Cleared | 6/8/2022 | LACDHS APPROVED |
Contact Information
| Contractor | Chon Edwin; Lic. No.: 790069-B | 2214 NEBRASKA ST WEST COVINA, CA 91792 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/28/2022 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 6/28/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 7/5/2022 | Partial Approval | JONATHAN QUACH |
| Final | 10/28/2022 | Partial Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 10/28/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 12/6/2022 | OK to Issue CofO | KATY RAMIREZ |
| Smoke Detectors | 12/6/2022 | Approved | KATY RAMIREZ |