2246 1/2 S BRONSON AVE 90018

Certificate Information: 2246 1/2 S BRONSON AVE 90018

Application / Permit
20016-10000-08339
Plan Check / Job No.
B20LA05871
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT
Permit Issued
Issued on 6/12/2020
Issuing Office
Current Status
CofO Issued on 12/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 LAMAR DAVIS
Corrections Issued 4/8/2020 LAMAR DAVIS
Quality Review Completed 4/15/2020 PRANITA SHAH
Plan Check Approved 6/3/2020 LAMAR DAVIS
Issued 6/12/2020 APPLICANT
CofO in Progress 10/19/2021 STUART CHAPMAN
Permit Finaled 12/15/2021 DEROLD HAUFF
CofO Issued 12/15/2021 DEROLD HAUFF
Permit Finaled 12/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/30/2020 RENZ SORIANO
Sewer availability Cleared 4/30/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 5/4/2020 RENZ SORIANO
Tenant Habitability Plan Cleared 5/14/2020 MICHAEL SOTO
Community Plan Implem. Overlay Cleared 5/29/2020 KYLE WINSTON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/5/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 4/5/2021 Partial Approval STUART CHAPMAN
Green Building Rough 4/5/2021 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 4/5/2021 Approved STUART CHAPMAN
METHANE-Rough 4/5/2021 Not Ready for Inspection STUART CHAPMAN
Deputy Drilled-In Anchors 4/14/2021 Conditional Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/16/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 4/16/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 4/16/2021 Approved STUART CHAPMAN
Green Building Rough 4/16/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 4/16/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 5/5/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/5/2021 Not Ready for Inspection STUART CHAPMAN
Wood Frame 5/5/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 7/6/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 7/6/2021 Not Ready for Inspection STUART CHAPMAN
Wood Frame 7/6/2021 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 7/22/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/22/2021 Approved STUART CHAPMAN
Green Building Rough 7/22/2021 Approved STUART CHAPMAN
METHANE-Rough 7/22/2021 Approved STUART CHAPMAN
PLUMBING-Rough 7/22/2021 Approved STUART CHAPMAN
Shower Pan 7/22/2021 Approved STUART CHAPMAN
Insulation 8/6/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 8/6/2021 Approved JESUS PINEDA
Drywall Nailing 8/10/2021 Approved STUART CHAPMAN
Special/Order Compliance 8/18/2021 Approved WILLIAM WREN
ELECTRICAL-Final 10/7/2021 No Access for Inspection JUSTIN HAWLEY
Final 10/7/2021 No Access for Inspection JUSTIN HAWLEY
Green Building Final 10/7/2021 No Access for Inspection JUSTIN HAWLEY
MERV13>=Final 10/7/2021 No Access for Inspection JUSTIN HAWLEY
PLUMBING-Final 10/7/2021 No Access for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 10/7/2021 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 10/7/2021 No Access for Inspection JUSTIN HAWLEY
Final 10/8/2021 Corrections Issued STUART CHAPMAN
Green Building Final 10/8/2021 Approved STUART CHAPMAN
MERV13>=Final 10/8/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 10/8/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 10/18/2021 Approved STUART CHAPMAN
Final 10/18/2021 OK to Issue CofO STUART CHAPMAN
HVAC-Final 10/18/2021 Approved STUART CHAPMAN
PLUMBING-Final 10/18/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Approved STUART CHAPMAN