14717 W POLK ST 91342
Certificate Information: 14717 W POLK ST 91342
- Application / Permit
- 20016-10000-08271
- Plan Check / Job No.
- B20LA05816
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT A 2 CAR GARAGE INTO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- CofO Issued on 10/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 6/22/2021 | OMAR GARNICA |
| Issued | 6/24/2021 | APPLICANT |
| CofO in Progress | 9/25/2024 | KEVIN BERBERYAN |
| Permit Finaled | 10/8/2024 | DANIEL ORRANTE |
| CofO Issued | 10/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/11/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 5/21/2021 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/14/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Sewer | 2/14/2024 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 2/16/2024 | Partial Approval | CRAIG DAVIS |
| Sewer | 2/16/2024 | Partial Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/8/2024 | Corrections Issued | KEVIN BERBERYAN |
| Underground Mechanical | 4/8/2024 | Corrections Issued | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 4/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 4/10/2024 | Partial Approval | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 4/12/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 5/1/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 5/1/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 5/30/2024 | Approved | KEVIN BERBERYAN |
| Gas Test | 5/30/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 5/30/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/30/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 5/30/2024 | Partial Approval | KEVIN BERBERYAN |
| Drywall Nailing | 6/12/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Insulation | 6/12/2024 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 6/12/2024 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/24/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 6/24/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 6/24/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 6/24/2024 | Approved | KEVIN BERBERYAN |
| Final | 8/13/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 8/13/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 8/13/2024 | Approved | KEVIN BERBERYAN |
| Final | 8/26/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/26/2024 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/26/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Final | 8/29/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 9/10/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 9/17/2024 | Approved | KEVIN BERBERYAN |