5506 E VALLEY BLVD 90032

Certificate Information: 5506 E VALLEY BLVD 90032

Application / Permit
20016-10000-08018
Plan Check / Job No.
B20LA05688
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL ORDINARY MOMENT FRAME.
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofC Issued on 1/19/2024

Permit Application Status History

Submitted 3/25/2020 APPLICANT
Assigned to Plan Check Engineer 4/15/2020 DANIEL SANJUAN
Corrections Issued 4/22/2020 DANIEL SANJUAN
Quality Review Completed 4/23/2020 HANS SANTIAGO
Applicant returned to address corrections 12/16/2020 DANIEL SANJUAN
Plan Check Approved 2/24/2021 DANIEL SANJUAN
Issued 4/15/2021 APPLICANT
OK for CofC 1/19/2024 DARRYL ARNOLD
CofC Issued 1/19/2024 WINSTON DUNNING

Permit Application Clearance Information

Historic Resource Verification Cleared 2/1/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 2/11/2021 DAVID URITA
Tenant Habitability Plan Cleared 4/14/2021 MICHAEL SOTO

Contact Information

Contractor Tarapaca Construction Inc; Lic. No.: 1061763-B 2275 HUNTINGTON DR SUITE 912      SAN MARINO, CA 91108
Engineer Zhuang,, Wenbin; Lic. No.: S5236 184 S ALTADENA DRIVE      PASADENA, CA 91107

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/11/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 5/14/2021 Partial Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 6/1/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 6/1/2021 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 6/1/2021 Not Ready for Inspection MARK FERRARI
Wood Frame 6/1/2021 Not Ready for Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 6/4/2021 Partial Inspection JONATHAN QUACH
Footing/Foundation/Slab 6/4/2021 Partial Inspection JONATHAN QUACH
Structural Steel Frame 6/4/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 6/4/2021 Partial Approval JONATHAN QUACH
Footing/Foundation/Slab 6/23/2021 Approved MARK FERRARI
Insulation 6/23/2021 Approved MARK FERRARI
Structural Steel Frame 6/23/2021 Approved MARK FERRARI
Wood Frame 6/23/2021 Approved MARK FERRARI
Drywall Nailing 6/29/2021 Approved MARK FERRARI
Insulation 6/29/2021 Approved MARK FERRARI
Interior/Exterior Lathing 6/29/2021 Approved MARK FERRARI
Final 7/27/2021 Conditional Approval MARK FERRARI
SGSOV-Seismic Gas S/O Valve 7/27/2021 SGSOV Approved MARK FERRARI
Smoke Detectors 7/27/2021 Approved MARK FERRARI
Special/Order Compliance 8/28/2023 Conditional Approval DARRYL ARNOLD
Final 1/19/2024 OK for CofC DARRYL ARNOLD