14650 W PARTHENIA ST 91402
Certificate Information: 14650 W PARTHENIA ST 91402
- Application / Permit
- 20016-10000-07996
- Plan Check / Job No.
- B20LA05667
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- Rooftop pv system on (E) commercial building. "COMPLY WITH DEPARTMENT ORDER effective date 08/17/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- Permit Finaled on 1/26/2021
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 4/22/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 5/14/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 6/3/2020 | APPLICANT |
| Applicant returned to address corrections | 7/28/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 8/6/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 9/3/2020 | CHUNG-WEN CHUANG |
| Issued | 9/10/2020 | APPLICANT |
| Permit Finaled | 1/26/2021 | HAMID PISHEHVAR |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/22/2020 | JOE LUCKEY |
| Supp. Use District POD/CDO/TDO | Cleared | 7/22/2020 | JOE LUCKEY |
| ZI | Cleared | 7/22/2020 | JOE LUCKEY |
| Solar Clearance | Cleared | 8/6/2020 | CHUNG-WEN CHUANG |
| Miscellaneous | Cleared | 9/1/2020 | OSCAR SALGADO JR |
Contact Information
| Contractor | Permacity Skybridge Corp; Lic. No.: 757547-B | 1415 N BATAVIA ORANGE, CA 92867 |
| Engineer | Vinci,, James Richard; Lic. No.: S4411 | 175 E WILBUR ROAD STE 103 THOUSAND OAKS, CA 91360 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/10/2020 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 12/15/2020 | Approved | ANDREW DORSO |
| Reinforced Concrete Frame | 12/15/2020 | Approved | ANDREW DORSO |
| Final | 12/23/2020 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 12/23/2020 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Final | 12/31/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| Final | 1/5/2021 | Not Ready for Inspection | ANDREW DORSO |
| Smoke Detectors | 1/5/2021 | Approved | ANDREW DORSO |
| Final | 1/26/2021 | Permit Finaled | HAMID PISHEHVAR |