5800 S CENTRAL AVE 90011

Certificate Information: 5800 S CENTRAL AVE 90011

Application / Permit
20016-10000-07978
Plan Check / Job No.
B20LA05648
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
CHANGE OF USE FROM WAREHOUSE TO OFFICE BUILDING (B-OCCUPANCY), AND INTERIOR REMODEL AND STRUCTURAL ALTERATION TO THE (E) BUILDING. EXTERIOR ALTERATION REMODEL EXTERIOR FINISH, DOORS AND WINDOWS. DEMO INTERIOR WALLS AND MEZZANINES, PROVIDE NEW REST ROOMS.
Permit Issued
Issued on 3/17/2021
Issuing Office
Current Status
CofO Issued on 7/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 RAHEL BEYENE
Corrections Issued 4/17/2020 RAHEL BEYENE
Quality Review Completed 4/17/2020 STANLEY RAAP
Disabled Access Plans Picked Up 4/17/2020 APPLICANT
Applicant returned to address corrections 7/27/2020 RAHEL BEYENE
Applicant returned to address corrections 10/7/2020 RAHEL BEYENE
Green Plans Picked Up 10/20/2020 APPLICANT
Plan Check Approved 3/8/2021 RAHEL BEYENE
Issued 3/17/2021 APPLICANT
Building Plans Picked Up 3/25/2021 APPLICANT
CofO in Progress 6/7/2022 RUSSELL BONVOULOIR
CofO Issued 7/1/2022 ERNESTO CORRAL
Permit Finaled 7/1/2022 ERNESTO CORRAL

Permit Application Clearance Information

CPC Cleared 5/14/2020 KENTON TRINH
Address approval Cleared 5/19/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/27/2020 JEANIE LAM
Redevelopment Project Area Cleared 5/27/2020 DAVID URITA
Sewer availability Cleared 5/27/2020 JEANIE LAM
Green Code Cleared 7/22/2020 VIVIAN LAO
ZI Cleared 10/8/2020 HELEN JADALI
DAS Clearance Cleared 11/12/2020 RAHEL BEYENE

Contact Information

Architect Han,, Sunjung; Lic. No.: C33851 3000 ANACAPA PLACE      FULLERTON, CA 92835
Contractor Owner-Builder       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/16/2021 Conditional Approval LANNY MERRICK
Deputy Drilled-In Anchors 4/20/2021 Conditional Approval LANNY MERRICK
Deputy Drilled-In Anchors 4/21/2021 Conditional Approval LANNY MERRICK
Deputy Drilled-In Anchors 4/22/2021 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 4/26/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 4/27/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 4/28/2021 Conditional Approval LANNY MERRICK
Pre-Inspection 4/28/2021 Partial Inspection DANIEL COLLINS
Deputy Reinf. Concrete 4/30/2021 Conditional Approval LEOPOLDO MENDOZA
Pre-Inspection 5/3/2021 Partial Inspection LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 5/5/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 5/6/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 5/6/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 5/7/2021 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 5/14/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 5/18/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 5/21/2021 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 5/24/2021 Corrections Issued JOEY BUCHANAN
Deputy Reinf. Concrete 5/25/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/15/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 6/18/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Wood Construction 7/16/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Wood Construction 7/21/2021 Conditional Approval LEOPOLDO MENDOZA
Green Building Rough 7/21/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 7/21/2021 Partial Approval LEOPOLDO MENDOZA
Green Building Rough 7/23/2021 Approved LEOPOLDO MENDOZA
Wood Frame 7/23/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Wood Construction 7/28/2021 Conditional Approval LEOPOLDO MENDOZA
Wood Frame 7/29/2021 Corrections Issued LEOPOLDO MENDOZA
Deputy Wood Construction 8/4/2021 Conditional Approval LEOPOLDO MENDOZA
Insulation 8/4/2021 Partial Approval LEOPOLDO MENDOZA
Interior/Exterior Lathing 8/6/2021 Partial Approval LEOPOLDO MENDOZA
Insulation 8/20/2021 Partial Approval LEOPOLDO MENDOZA
Wood Frame 8/20/2021 Approved LEOPOLDO MENDOZA
Interior/Exterior Lathing 8/30/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 9/1/2021 Approved LEOPOLDO MENDOZA
Insulation 9/29/2021 Approved LEOPOLDO MENDOZA
T-Bar Ceiling 12/21/2021 Approved RUSSELL BONVOULOIR
Footing/Foundation/Slab 2/7/2022 Partial Approval RUSSELL BONVOULOIR
Pre-Inspection 2/25/2022 Conditional Approval DARRYL ARNOLD
Final 3/29/2022 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 3/29/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 3/29/2022 Conditional Approval DARRYL ARNOLD
Final 6/3/2022 Conditional Approval RUSSELL BONVOULOIR
Green Building Final 6/3/2022 Approved RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Approved RUSSELL BONVOULOIR
Smoke Detectors 6/3/2022 Approved RUSSELL BONVOULOIR