2922 S BUDLONG AVE 90007
Certificate Information: 2922 S BUDLONG AVE 90007
- Application / Permit
- 20016-10000-07954
- Plan Check / Job No.
- B20LA05628
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (3) STEEL SPECIAL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/25/2025
Permit Application Status History
| Submitted | 3/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2020 | DANIEL SANJUAN |
| Corrections Issued | 4/24/2020 | DANIEL SANJUAN |
| Quality Review Completed | 4/28/2020 | SAI KHUM |
| Plan Check Approved | 7/24/2020 | DANIEL SANJUAN |
| Issued | 7/18/2023 | APPLICANT |
| OK for CofC | 2/25/2025 | DARRYL ARNOLD |
| CofC Issued | 2/25/2025 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/13/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | M Y Construction Inc; Lic. No.: 1036168-B | 10116 HILLGROVE DRIVE BEVERLY HILLS, CA 90210 |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 5649 VANTAGE AVE VALLEY VILLAGE, CA 91607 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2023 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 8/10/2023 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 8/14/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Other (see comments) | 2/29/2024 | Partial Approval | JACOB MYERS |
| Deputy Steel/Welding | 2/29/2024 | Partial Approval | JACOB MYERS |
| Excavation/Setback/Form/Re-Bar | 3/8/2024 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/8/2024 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 3/8/2024 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 3/11/2024 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 5/2/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 5/2/2024 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 5/6/2024 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/14/2024 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/9/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 7/15/2024 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Final | 7/15/2024 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 7/15/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 2/25/2025 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 2/25/2025 | Approved | DARRYL ARNOLD |