5461 N FIGUEROA ST Unit A & B 90042
Certificate Information: 5461 N FIGUEROA ST Unit A & B 90042
- Application / Permit
- 20016-10000-07905
- Plan Check / Job No.
- B20LA05601
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- SUBDIVIDE (E) TENANT SPACE INTO (2) NEW SPACES. CONVERT (E) RETAIL SPACE TO A (N) RETAIL AND (N) FUTURE TENANT SPACE. WORK INCLUDES REMOVE EXTERIOR WALL FINISH, REMODEL STORE FRONT WITH (N) STOREFRONT ENTRY, INTERIOR WALL FINISH AND PARTIAL ROOF REPAIR. T.I WITH (N) REFRIDGERATION W/ VANILLA SHELL AND (N) RTU.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 11/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | RACHEL BEYENE |
| Corrections Issued | 4/3/2020 | RACHEL BEYENE |
| Quality Review Completed | 4/8/2020 | STANLEY RAAP |
| Green Plans Picked Up | 6/22/2020 | APPLICANT |
| Applicant returned to address corrections | 9/24/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 10/1/2020 | RACHEL BEYENE |
| Plan Check Approved | 10/9/2020 | RAHEL BEYENE |
| Issued | 10/9/2020 | APPLICANT |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| TCO Issued (Expire Date: 06-05-2021) | 12/7/2020 | ERNESTO CORRAL |
| CofO in Progress | 11/30/2021 | ERNESTO CORRAL |
| CofO Issued | 11/30/2021 | ERNESTO CORRAL |
| Permit Finaled | 11/30/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 4/27/2020 | MAXFIELD VERMY |
| "Q" conditions | Cleared | 4/27/2020 | MAXFIELD VERMY |
| CPC | Cleared | 4/27/2020 | MAXFIELD VERMY |
| Address approval | Cleared | 5/7/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 5/7/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 5/7/2020 | CECILIO NAVARRO |
| HPOZ | Cleared | 5/14/2020 | KATIE DEBIASE |
| Metro Rail approval | Cleared | 5/19/2020 | RAHEL BEYENE |
| Specific Plan | Cleared | 6/3/2020 | ADRINEH MELKONIAN |
| Green Code | Cleared | 6/22/2020 | VIVIAN LAO |
| DAS Clearance | Cleared | 9/3/2020 | ELIZABETH TOMS |
| ZA Case | Cleared | 9/29/2020 | CLAUDE GOODING |
| ZI | Cleared | 10/9/2020 | GRACIELA ACOSTA |
Contact Information
| Architect | Heath,, Dennis Michael; Lic. No.: C12815 | MBH ARCHITECTS 960 ATLANTIC AVE. ALAMEDA, CA 94501 |
| Contractor | Tilton Pacific Construction Inc; Lic. No.: 488531-B | 4150 CITRUS AVENUE ROCKLIN, CA 95677 |
| Engineer | Elliott,, Justin J; Lic. No.: S6267 | 3933 SE KELLY AVE PORTLAND, OR 97239 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 10/19/2020 | Not Ready for Inspection | RONALD PACHECO |
| Light Gage Steel Frame | 10/19/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 10/19/2020 | Partial Approval | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 10/22/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Rough | 10/22/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 10/22/2020 | Not Ready for Inspection | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 10/26/2020 | Partial Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 10/27/2020 | Conditional Approval | RONALD PACHECO |
| Drywall Nailing | 10/29/2020 | Partial Approval | RONALD PACHECO |
| Light Gage Steel Frame | 10/29/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 10/30/2020 | Partial Approval | RONALD PACHECO |
| Light Gage Steel Frame | 10/30/2020 | Not Ready for Inspection | RONALD PACHECO |
| Structural Steel Frame | 10/30/2020 | Not Ready for Inspection | RONALD PACHECO |
| Deputy Drilled-In Anchors | 11/2/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Masonry | 11/2/2020 | Conditional Approval | RONALD PACHECO |
| Drywall Nailing | 11/2/2020 | Partial Approval | LANNY MERRICK |
| Light Gage Steel Frame | 11/2/2020 | Partial Approval | LANNY MERRICK |
| Drywall Nailing | 11/4/2020 | Partial Approval | RONALD PACHECO |
| Insulation | 11/4/2020 | Partial Approval | RONALD PACHECO |
| Light Gage Steel Frame | 11/4/2020 | Partial Approval | RONALD PACHECO |
| Masonry Wall/Backfill | 11/4/2020 | Partial Approval | RONALD PACHECO |
| Structural Steel Frame | 11/4/2020 | Corrections Issued | RONALD PACHECO |
| Drywall Nailing | 11/6/2020 | Partial Approval | RONALD PACHECO |
| Masonry Wall/Backfill | 11/6/2020 | Partial Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 11/10/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 11/10/2020 | Conditional Approval | RONALD PACHECO |
| Green Building Rough | 11/16/2020 | Approved | RONALD PACHECO |
| Wood Frame | 11/16/2020 | Partial Approval | RONALD PACHECO |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Partial Inspection | RONALD PACHECO |
| Drywall Nailing | 11/20/2020 | Partial Approval | RONALD PACHECO |
| Pre-Inspection | 11/24/2020 | Not Ready for Inspection | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 11/30/2020 | SGSOV Not Ready | RONALD PACHECO |
| Final | 12/4/2020 | Partial Approval | RONALD PACHECO |
| Green Building Final | 12/4/2020 | Approved | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 12/4/2020 | SGSOV Approved | RONALD PACHECO |
| Smoke Detectors | 12/4/2020 | Approved | RONALD PACHECO |
| Wood Frame | 12/4/2020 | Approved | RONALD PACHECO |
| Final | 12/7/2020 | Partial Approval | RONALD PACHECO |
| Final | 12/30/2020 | Not Ready for Inspection | LANNY MERRICK |
| Final | 3/3/2021 | Conditional Approval | RONALD PACHECO |
| Special/Order Compliance | 5/12/2021 | Partial Inspection | LANNY MERRICK |