2858 N HERKIMER ST 90039

Certificate Information: 2858 N HERKIMER ST 90039

Application / Permit
20016-10000-07791
Plan Check / Job No.
B20LA05491
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERTING ATTACHED GARAGE TO ADU (328 SF).
Permit Issued
Issued on 7/2/2020
Issuing Office
Current Status
CofO Issued on 10/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 TSE MING HUANG
Corrections Issued 3/23/2020 TSE MING HUANG
Applicant returned to address corrections 5/4/2020 TSE MING HUANG
Applicant returned to address corrections 6/5/2020 TSE MING HUANG
Plan Check Approved 7/2/2020 TSE MING HUANG
Issued 7/2/2020 APPLICANT
Building Plans Picked Up 7/15/2020 APPLICANT
CofO in Progress 10/15/2021 JOSEPH MCGARRY
Permit Finaled 10/20/2021 DEROLD HAUFF
CofO Issued 10/20/2021 DEROLD HAUFF
Permit Finaled 10/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2020 JEANIE LAM
Address approval Cleared 5/12/2020 JEANIE LAM
Sewer availability Cleared 5/12/2020 JEANIE LAM
Grading Pre-Inspection Cleared 5/29/2020 VASIL MIHALEV

Contact Information

Contractor Flores Miguel; Lic. No.: 841528-B 420 GENOA STREET      ARCADIA, CA 91006
Engineer Acciani,, Mark; Lic. No.: C83929 PO BOX 1390      RUNNING SPRINGS, CA 92382

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/29/2020 Approved ARTHUR SARGSYAN
Pre-Inspection 9/2/2020 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 9/24/2020 Conditional Approval JOSEPH MCGARRY
PLUMBING-Rough 10/19/2020 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 10/29/2020 No Access for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 10/30/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 11/25/2020 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 11/25/2020 Approved JOSEPH MCGARRY
HVAC-Rough 11/25/2020 Not Ready for Inspection JOSEPH MCGARRY
MERV13>=Rough 11/25/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 11/25/2020 Approved JOSEPH MCGARRY
Insulation 1/4/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/4/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Wood Construction 1/5/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Conditional Approval HAMIK HARTOUNIAN
Insulation 1/8/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/8/2021 Partial Approval HAMIK HARTOUNIAN
Shower Pan 1/8/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 1/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/2/2021 Approved JOSEPH MCGARRY
Drywall Nailing 2/2/2021 Approved JOSEPH MCGARRY
Insulation 2/2/2021 Approved JOSEPH MCGARRY
Shower Pan 2/2/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 2/24/2021 Approved JOSEPH MCGARRY
Final 5/24/2021 Not Ready for Inspection JOSEPH MCGARRY
MERV13>=Final 5/24/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 5/24/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 5/24/2021 Approved JOSEPH MCGARRY
Final 8/31/2021 Corrections Issued JOSEPH MCGARRY
Final 9/13/2021 Not Ready for Inspection JOSEPH MCGARRY
Final 10/13/2021 OK to Issue CofO JOSEPH MCGARRY