2839 S WIGTOWN ROAD 90064

Certificate Information: 2839 S WIGTOWN ROAD 90064

Application / Permit
20016-10000-07742
Plan Check / Job No.
B20LA05446
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ALTERATION TO SFD: FULL KITCHEN REMODEL, NEW DOORS, REPLACE 2 DOORS, WINDOWS, NEW INTERIOR STEPS. ADD [5x10x 4 ft High] WOOD DECK
Permit Issued
Issued on 4/24/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 3/31/2021

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/18/2020 JESSE JIMENEZ
Corrections Issued 3/18/2020 JESSE JIMENEZ
Plan Check Approved 3/20/2020 KEVIN MORALES
Issued 4/24/2020 LADBS
Permit Finaled 3/31/2021 KEVIN SARGSYAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/19/2020 PATRICK MISCHLICH

Contact Information

Contractor Blue Coast Inc; Lic. No.: 614146-B PO BOX 5562      SANTA MONICA, CA 904095562
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/2/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/2/2020 Approved KEVIN SARGSYAN
Pre-Inspection 7/2/2020 Partial Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 7/23/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 7/23/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/30/2020 Approved KEVIN SARGSYAN
Wood Frame 7/30/2020 Approved KEVIN SARGSYAN
Drywall Nailing 8/14/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 8/14/2020 Approved KEVIN SARGSYAN
Final 3/23/2021 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 3/23/2021 Approved KEVIN SARGSYAN
Final 3/31/2021 Permit Finaled KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/31/2021 SGSOV Approved KEVIN SARGSYAN