4254 W 5TH ST 90020
Certificate Information: 4254 W 5TH ST 90020
- Application / Permit
- 20016-10000-07706
- Plan Check / Job No.
- B20LA05429
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 2070 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL PLYWOOD SHEAR WALL, STEEL MOMENT FRAME, AND STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 10/14/2020
- Issuing Office
- Current Status
- CofC Issued on 5/24/2021
Permit Application Status History
| Submitted | 3/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2020 | VARAND SARKISIAN |
| Corrections Issued | 4/6/2020 | VARAND SARKISIAN |
| Quality Review Completed | 4/9/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 5/21/2020 | VARAND SARKISIAN |
| Plan Check Approved | 6/1/2020 | VARAND SARKISIAN |
| Issued | 10/14/2020 | APPLICANT |
| OK for CofC | 5/13/2021 | DARRYL ARNOLD |
| CofC Issued | 5/24/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 5/26/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 5/28/2020 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 9/14/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 5104 GARDEN GROVE AVE TARZANA, CA 91356 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/15/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 2/11/2021 | Conditional Approval | FRED WOHLFARTH |
| Deputy Drilled-In Anchors | 2/17/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 2/22/2021 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 2/22/2021 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 2/22/2021 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 2/22/2021 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 2/24/2021 | Conditional Approval | FRED WOHLFARTH |
| Deputy Wood Construction | 3/2/2021 | Conditional Approval | FRED WOHLFARTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2021 | Partial Inspection | MARK FERRARI |
| Wood Frame | 3/5/2021 | Corrections Issued | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 3/15/2021 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 3/31/2021 | Approved | DARRYL ARNOLD |
| Final | 5/13/2021 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/13/2021 | Approved | DARRYL ARNOLD |