4254 W 5TH ST 90020

Certificate Information: 4254 W 5TH ST 90020

Application / Permit
20016-10000-07706
Plan Check / Job No.
B20LA05429
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN 2070 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL PLYWOOD SHEAR WALL, STEEL MOMENT FRAME, AND STEEL CANTILEVER COLUMN.
Permit Issued
Issued on 10/14/2020
Issuing Office
Current Status
CofC Issued on 5/24/2021

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/25/2020 VARAND SARKISIAN
Corrections Issued 4/6/2020 VARAND SARKISIAN
Quality Review Completed 4/9/2020 HANS SANTIAGO
Applicant returned to address corrections 5/21/2020 VARAND SARKISIAN
Plan Check Approved 6/1/2020 VARAND SARKISIAN
Issued 10/14/2020 APPLICANT
OK for CofC 5/13/2021 DARRYL ARNOLD
CofC Issued 5/24/2021 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 5/26/2020 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 5/28/2020 DAVID URITA
Tenant Habitability Plan Cleared 9/14/2020 STEVEN HOFSTAD

Contact Information

Contractor Sks Construction; Lic. No.: 720390-B 5104 GARDEN GROVE AVE      TARZANA, CA 91356
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 5104 GARDEN GROVE      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2020 Approved MARK FERRARI
Deputy Steel/Welding 2/11/2021 Conditional Approval FRED WOHLFARTH
Deputy Drilled-In Anchors 2/17/2021 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 2/22/2021 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 2/22/2021 Approved JONATHAN QUACH
Structural Steel Frame 2/22/2021 Partial Approval JONATHAN QUACH
Wood Frame 2/22/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 2/24/2021 Conditional Approval FRED WOHLFARTH
Deputy Wood Construction 3/2/2021 Conditional Approval FRED WOHLFARTH
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Partial Inspection MARK FERRARI
Wood Frame 3/5/2021 Corrections Issued MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Approved JONATHAN QUACH
Wood Frame 3/15/2021 Approved JONATHAN QUACH
Interior/Exterior Lathing 3/31/2021 Approved DARRYL ARNOLD
Final 5/13/2021 OK for CofC DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 5/13/2021 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 5/13/2021 Approved DARRYL ARNOLD