4625 N SYLMAR AVE 91423
Certificate Information: 4625 N SYLMAR AVE 91423
- Application / Permit
- 20016-10000-07607
- Plan Check / Job No.
- B20LA05353
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CREATE 2 ATTACHED ADUS PER STATE LAW GCS 65852.2(E)(1)(C) IN EXISITING 29 UNIT APARTMENT. CONVERTING STORAGE ROOM AND MANAGER OFFICE
- Permit Issued
- Issued on 9/21/2021
- Issuing Office
- Current Status
- CofO Issued on 7/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2020 | STARR CHEN |
| Corrections Issued | 4/2/2020 | STARR CHEN |
| Quality Review Completed | 4/8/2020 | LAWRENCE QUIRANTE |
| Disabled Access Plans Picked Up | 4/30/2020 | APPLICANT |
| Building Plans Picked Up | 6/18/2020 | APPLICANT |
| Applicant returned to address corrections | 10/7/2020 | STARR CHEN |
| Plan Check Approved | 3/26/2021 | STARR CHEN |
| Plan Check Approved | 9/21/2021 | STARR CHEN |
| Issued | 9/21/2021 | APPLICANT |
| Permit Finaled | 7/22/2024 | RICKEY JACKSON |
| CofO Issued | 7/22/2024 | RICKEY JACKSON |
| Permit Finaled | 7/22/2024 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/26/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2020 | ADRIAN CASTRO |
| DAS Clearance | Cleared | 8/17/2020 | EDDIE GARIN |
| Green Code | Cleared | 8/27/2020 | STARR CHEN |
| ZI | Cleared | 10/8/2020 | RICHARD REASER |
| Fire Marshal Fire Life Safety | Cleared | 3/17/2021 | MENOA AGHAJANI |
Contact Information
| Contractor | Jim Su; Lic. No.: 1028936-B | 667 EASTMONT AVE LOS ANGELES, CA 90022 |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 5649 VANTAGE AVE VALLEY VILLAGE, CA 91607 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2022 | Partial Inspection | CAMERON CHABAN |
| Green Building Rough | 3/8/2022 | Approved | CAMERON CHABAN |
| Wood Frame | 3/8/2022 | Partial Inspection | CAMERON CHABAN |
| Wood Frame | 3/30/2022 | Not Ready for Inspection | JEFFREY DURAN |
| Wood Frame | 4/14/2022 | Conditional Approval | CAMERON CHABAN |
| Insulation | 4/28/2022 | Partial Approval | JEFFREY DURAN |
| Insulation | 5/24/2022 | Approved | CAMERON CHABAN |
| Drywall Nailing | 6/14/2022 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 6/14/2022 | Approved | ROBERT DAVIS |
| Final | 8/3/2022 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 8/3/2022 | Not Ready for Inspection | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV No Gas | CAMERON CHABAN |
| Smoke Detectors | 8/3/2022 | Approved | CAMERON CHABAN |
| Wood Frame | 8/3/2022 | Approved | CAMERON CHABAN |
| Final | 6/13/2024 | Conditional Approval | STEVEN LEVITT |
| Green Building Final | 6/13/2024 | Approved | STEVEN LEVITT |