270 W 42ND PL 90037
Certificate Information: 270 W 42ND PL 90037
- Application / Permit
- 20016-10000-07604
- Plan Check / Job No.
- B20LA05351
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT EXISTING STORAGE INTO AN ACCESSORY DWELLING UNIT IN AN EXISTING MIXED USE BUILDING PER STATE LAW GCS 65852.2(e)(1)(C).
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 4/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | MICHAEL LOPEZ |
| Corrections Issued | 4/9/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 4/9/2020 | QUAN NGHIEM |
| Applicant returned to address corrections | 6/25/2020 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/15/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 10/1/2020 | MICHAEL LOPEZ |
| Issued | 10/9/2020 | APPLICANT |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| CofO in Progress | 4/19/2021 | LANNY MERRICK |
| CofO Issued | 4/19/2021 | ERNESTO CORRAL |
| Permit Finaled | 4/19/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| CPC | Cleared | 5/7/2020 | RUBEN VASQUEZ |
| CPC | Cleared | 5/7/2020 | RUBEN VASQUEZ |
| ZA Case | Cleared | 5/7/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 5/8/2020 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 5/8/2020 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2020 | WALLIE JONG |
| Sewer availability | Cleared | 5/11/2020 | WALLIE JONG |
| Redevelopment Project Area | Cleared | 6/5/2020 | GRACIELA ACOSTA |
| DAS Clearance | Cleared | 8/31/2020 | MICHAEL LOPEZ |
Contact Information
| Contractor | B & S Construction Inc; Lic. No.: 848067-B | 326 S WESTLAKE AVENUE #103 LOS ANGELES, CA 90057 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/15/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 10/15/2020 | SGSOV Not Ready | LEOPOLDO MENDOZA |
| Smoke Detectors | 10/15/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 10/15/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 12/4/2020 | Corrections Issued | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 12/4/2020 | SGSOV Not Ready | LEOPOLDO MENDOZA |
| Smoke Detectors | 12/4/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 12/4/2020 | Approved | LEOPOLDO MENDOZA |
| Final | 2/22/2021 | Not Ready for Inspection | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 2/22/2021 | SGSOV Approved | LANNY MERRICK |
| Smoke Detectors | 2/22/2021 | Approved | LANNY MERRICK |
| Final | 2/25/2021 | Corrections Issued | LANNY MERRICK |
| Final | 3/23/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 4/19/2021 | OK to Issue CofO | LANNY MERRICK |