11940 N EDDLESTON DR 91326
Certificate Information: 11940 N EDDLESTON DR 91326
- Application / Permit
- 20016-10000-07553
- Plan Check / Job No.
- B20LA05308
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & 78 s.f ADDITION TO (E) SINGLE FAMILY DWELLING DUE TO FIRE DAMAGE .
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Current Status
- CofO Issued on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | GARO TELMI |
| Corrections Issued | 3/23/2020 | GARO TELMI |
| Quality Review Completed | 3/23/2020 | KEN GILL |
| Building Plans Picked Up | 4/2/2020 | APPLICANT |
| Green Plans Picked Up | 4/30/2020 | APPLICANT |
| Plan Check Approved | 5/13/2020 | GARO TELMI |
| Issued | 6/3/2020 | APPLICANT |
| CofO in Progress | 11/17/2021 | DAVID SCANTLIN |
| Permit Finaled | 11/17/2021 | JOHN JANSON |
| CofO Issued | 11/17/2021 | JOHN JANSON |
| Permit Finaled | 11/17/2021 | JOHN JANSON |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 4/14/2020 | SARAHI ORTEGA |
| Low Impact Development | Cleared | 4/21/2020 | ORVAL HERNANDEZ-MARCIAL |
| Grading Pre-Inspection | Cleared | 4/24/2020 | VASIL MIHALEV |
| Green Code | Cleared | 4/29/2020 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 5/7/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Fair Oaks Construction Inc; Lic. No.: 977445-B | 26542 CARDINAL DRIVE CANYON COUNTRY, CA 91387 |
| Engineer | Lubberts,, Jeffrey Scott; Lic. No.: S6432 | 2022 DEWBERRY CT WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/10/2020 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/10/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/10/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 2/9/2021 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/10/2021 | Partial Approval | DAVID SCANTLIN |
| Green Building Rough | 3/10/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| METHANE-Rough | 3/10/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Wood Construction | 3/17/2021 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/24/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 3/24/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| METHANE-Rough | 3/24/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 4/28/2021 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 4/28/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 4/28/2021 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 4/28/2021 | Approved | DAVID SCANTLIN |
| Insulation | 5/7/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/13/2021 | Partial Approval | STEPHANIE SWANSON |
| Pre-Inspection | 5/13/2021 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 6/16/2021 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 6/16/2021 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 8/20/2021 | Approved | DEANDRE HOFFMAN |
| Shower Pan | 8/20/2021 | Approved | DEANDRE HOFFMAN |
| Gas Test | 8/24/2021 | Partial Inspection | DEANDRE HOFFMAN |
| Gas Test | 8/27/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/5/2021 | Approved | DAVID SCANTLIN |
| Final | 11/5/2021 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 11/5/2021 | Approved | DAVID SCANTLIN |
| Green Building Final | 11/5/2021 | Approved | DAVID SCANTLIN |
| METHANE-Barrier | 11/5/2021 | Approved | DAVID SCANTLIN |
| METHANE-Final | 11/5/2021 | Approved | DAVID SCANTLIN |
| METHANE-Rough | 11/5/2021 | Approved | DAVID SCANTLIN |
| METHANE-Subgrade | 11/5/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 11/5/2021 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 11/5/2021 | Approved | DAVID SCANTLIN |
| Final | 11/16/2021 | OK to Issue CofO | DAVID SCANTLIN |