12971 N LOUISE AVE 91344

Certificate Information: 12971 N LOUISE AVE 91344

Application / Permit
20016-10000-07546
Plan Check / Job No.
B20LA05302
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ALTERATION TO SFD TO ADD NEW DOOR SYSTEMS, REMODEL KITCHEN AREA , REMODEL ALL BATHROOMS, REMOVE AND REPLACE INTERIOR STAIRS, ADD CLOSET TO MASTERBEDROOM AND REPLACE ALL WINDOWS
Permit Issued
Issued on 6/23/2020
Issuing Office
Valley
Current Status
Permit Finaled on 12/8/2022

Permit Application Status History

Submitted 3/16/2020 APPLICANT
Assigned to Plan Check Engineer 3/18/2020 SINA KHOSRAVI
Corrections Issued 3/19/2020 SINA KHOSRAVI
Applicant returned to address corrections 5/19/2020 AMIR DANAI
Plan Check Approved 5/28/2020 AMIR DANAI
Building Plans Picked Up 5/29/2020 APPLICANT
Issued 6/23/2020 LADBS
Permit Finaled 12/8/2022 DAVID SCANTLIN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/27/2020 BRIAN MILLER

Contact Information

Contractor Working Class American Construction; Lic. No.: 1053998-B 5115 W. AVE L10      QUARTZ HILL, CA 93536
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/29/2020 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 12/30/2020 Approved DAVID SCANTLIN
ELECTRICAL-Rough 4/1/2021 No Access for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 4/7/2021 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 4/7/2021 Approved VINCENT HANLEY
PLUMBING-Rough 4/20/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 6/18/2021 Approved DAVID SCANTLIN
HVAC-Rough 6/18/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 6/18/2021 Partial Approval DAVID SCANTLIN
Interior/Exterior Lathing 6/21/2021 Approved JUSTIN HAWLEY
Insulation 6/22/2021 Not Ready for Inspection JUSTIN HAWLEY
Insulation 6/25/2021 Approved DAVID SCANTLIN
Insulation 7/2/2021 Not Ready for Inspection RYAN SALAZAR
Drywall Nailing 7/12/2021 Approved KRISTEN CAUSEY
Shower Pan 9/2/2021 Approved DEANDRE HOFFMAN
Final 10/31/2022 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 10/31/2022 Approved SEAN HAUPT
Final 11/8/2022 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved HENRY KIM
Final 12/8/2022 Permit Finaled DAVID SCANTLIN