2079 W BLAKE AVE 90039
Certificate Information: 2079 W BLAKE AVE 90039
- Application / Permit
- 20016-10000-07540
- Plan Check / Job No.
- B20LA05297
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ADD 2ND FLOOR AND 1ST FLOOR ADDITION TO EXISITNG WAREHOUSE (15FT X 45FT, 675 SQFT), CHANGE OF USE FROM WAREHOUSE TO OFFICE.
- Permit Issued
- Issued on 9/25/2020
- Issuing Office
- Current Status
- CofO Issued on 6/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | TSE MING HUANG |
| Corrections Issued | 4/2/2020 | TSE MING HUANG |
| Quality Review Completed | 4/8/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 6/10/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 6/10/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 8/4/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 8/28/2020 | TSE MING HUANG |
| Plan Check Approved | 9/25/2020 | TSE MING HUANG |
| Issued | 9/25/2020 | APPLICANT |
| Building Plans Picked Up | 9/28/2020 | APPLICANT |
| CofO in Progress | 6/7/2023 | ERNESTO CORRAL |
| Permit Finaled | 6/7/2023 | ERNESTO CORRAL |
| CofO Issued | 6/7/2023 | ERNESTO CORRAL |
| Permit Finaled | 6/7/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2020 | CECILIO NAVARRO |
| Address approval | Cleared | 7/22/2020 | JEANIE LAM |
| Highway dedication | Cleared | 7/22/2020 | JEANIE LAM |
| Sewer availability | Cleared | 9/9/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 9/11/2020 | MARTIN FRAGOSO |
| DAS Clearance | Cleared | 9/17/2020 | TSE MING HUANG |
| "Q" conditions | Cleared | 9/21/2020 | TERRI OSBORNE |
| CPC | Cleared | 9/21/2020 | TERRI OSBORNE |
| ZI | Cleared | 9/21/2020 | TERRI OSBORNE |
| ZI | Cleared | 9/21/2020 | TERRI OSBORNE |
| Roof/Waste drainage to street | Cleared | 9/24/2020 | CECILIO NAVARRO |
| Green Code | Cleared | 9/25/2020 | TSE MING HUANG |
Contact Information
| Architect | Mulcahy,, Kevin Patrick; Lic. No.: C31272 | 3048 N. COOLIDGE AVENUE LOS ANGELES, CA 90039 |
| Contractor | Arroyo Hill Development Inc; Lic. No.: 889164-B | 3579 E FOOTHILL BLVD 311 LOS ANGELES, CA 91107 |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2021 | Partial Approval | LANNY MERRICK |
| Special/Order Compliance | 1/28/2021 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 2/12/2021 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 3/4/2021 | Partial Approval | RONALD PACHECO |
| Green Building Rough | 4/1/2021 | Not Ready for Inspection | LANNY MERRICK |
| Wood Frame | 4/1/2021 | Partial Approval | LANNY MERRICK |
| Insulation | 4/15/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 4/15/2021 | Partial Approval | MARK FERRARI |
| Green Building Rough | 4/23/2021 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 4/23/2021 | Partial Approval | MARK FERRARI |
| Green Building Rough | 6/9/2021 | Approved | MARK FERRARI |
| Wood Frame | 6/9/2021 | Conditional Approval | MARK FERRARI |
| Special/Order Compliance | 7/2/2021 | Partial Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 8/10/2021 | Approved | MARK FERRARI |
| Drywall Nailing | 8/18/2021 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 6/3/2022 | Approved | MARK FERRARI |
| Final | 6/3/2022 | Partial Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 6/3/2022 | Approved | MARK FERRARI |
| Green Building Final | 6/3/2022 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV No Gas | MARK FERRARI |
| Smoke Detectors | 6/3/2022 | Approved | MARK FERRARI |
| Wood Frame | 6/3/2022 | Approved | MARK FERRARI |
| Final | 5/5/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 5/5/2023 | Partial Approval | RAFAEL CORTES |
| Final | 5/22/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 5/22/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 6/2/2023 | OK to Issue CofO | RAFAEL CORTES |
| Green Building Final | 6/2/2023 | Approved | RAFAEL CORTES |