8155 N VAN NUYS BLVD 91402
Certificate Information: 8155 N VAN NUYS BLVD 91402
- Application / Permit
- 20016-10000-07509
- Plan Check / Job No.
- B20LA05286
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of use from Retail to Restaurant with multiple kitchens.
- Permit Issued
- Issued on 3/5/2021
- Issuing Office
- Current Status
- CofO Issued on 8/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2020 | SALVADOR QUINTANILLA |
| Corrections Issued | 3/17/2020 | SALVADOR QUINTANILLA |
| Plan Check Approved | 2/25/2021 | SALVADOR QUINTANILLA |
| Issued | 3/5/2021 | APPLICANT |
| Building Plans Picked Up | 3/12/2021 | APPLICANT |
| CofO in Progress | 8/1/2023 | ANDREW DORSO |
| CofO Issued | 8/1/2023 | JEFFREY DURAN |
| Permit Finaled | 8/1/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/23/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 7/23/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 7/23/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 7/23/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 7/23/2020 | SARAHI ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/4/2020 | ADRIAN CASTRO |
| "Q" conditions | Cleared | 8/24/2020 | PEGGY MALONE-BROWN |
| Supp. Use District POD/CDO/TDO | Cleared | 8/24/2020 | PEGGY MALONE-BROWN |
| Fire Marshall Fire Life Safety | Cleared | 10/8/2020 | MENOA AGHAJANI |
| Food Service Establishment | Cleared | 2/2/2021 | KENNETH BROWNE |
| Food establishment approval | Cleared | 2/25/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Ds Builders Group Inc; Lic. No.: 1045516-B | 22647 VENTURA BOULEVARD #534 WOODLAND HILLS, CA 91364 |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Structural Steel Frame | 6/28/2021 | Corrections Issued | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 7/13/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 9/17/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 11/18/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 1/18/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 2/7/2022 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 3/9/2022 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 3/24/2022 | Partial Approval | ROBERT DAVIS |
| Reinforced Concrete Frame | 4/13/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 5/6/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 5/23/2022 | Approved | JEFFREY FULTON |
| Drywall Nailing | 6/3/2022 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/3/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 6/8/2022 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/8/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 6/13/2022 | Approved | ANDREW DORSO |
| Final | 7/28/2023 | OK to Issue CofO | ANDREW DORSO |
| Green Building Final | 7/28/2023 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 7/28/2023 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 7/28/2023 | Approved | ANDREW DORSO |