5115 E ECHO ST 90042
Certificate Information: 5115 E ECHO ST 90042
- Application / Permit
- 20016-10000-07488
- Plan Check / Job No.
- B20LA05268
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTION OF (E) GARAGE TO DETACHED ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A) ALL WORK PER WFPP
- Permit Issued
- Issued on 7/30/2020
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2020 | MONICA RAMIREZ |
| Corrections Issued | 3/17/2020 | MONICA RAMIREZ |
| Building Plans Picked Up | 3/20/2020 | APPLICANT |
| Applicant returned to address corrections | 6/25/2020 | FERNANDO FLORES |
| Plan Check Approved | 7/30/2020 | FERNANDO FLORES |
| Issued | 7/30/2020 | APPLICANT |
| CofO in Progress | 2/2/2023 | AMY COLIN |
| Permit Finaled | 2/14/2023 | DANIEL ORRANTE |
| CofO Issued | 2/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2020 | JUAN ASHTON |
| "D" conditions | Cleared | 4/15/2020 | NOAH MCCOY |
| "Q" conditions | Cleared | 4/15/2020 | NOAH MCCOY |
| HPOZ | Cleared | 4/27/2020 | KATIE DEBIASE |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2020 | PAMELA TENEZA |
| Construction near power lines | Cleared | 5/27/2020 | RIDWAN HARDY |
| ZI | Cleared | 6/5/2020 | ADRINEH MELKONIAN |
| Sewer availability | Cleared | 6/16/2020 | ELAINE LEI |
| Hist. Property Cntrct Mgr Appr | Cleared | 7/20/2020 | LAMBERT GIESSINGER |
Contact Information
| No Data Available. |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/5/2020 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/5/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/5/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 9/18/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/22/2021 | Not Ready for Inspection | COREY HUPP |
| MERV13>=Rough | 7/22/2021 | Not Ready for Inspection | COREY HUPP |
| Pre-Inspection | 7/22/2021 | Partial Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 12/1/2021 | Partial Approval | COREY HUPP |
| MERV13>=Rough | 12/1/2021 | Not Ready for Inspection | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 12/1/2021 | Not Ready for Inspection | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 12/7/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 12/10/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 12/10/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/10/2021 | Partial Approval | HAMIK HARTOUNIAN |
| MERV13>=Rough | 12/10/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/20/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 12/20/2021 | Approved | AMY COLIN |
| Service/Power Release | 4/13/2022 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Final | 4/18/2022 | Approved | AMY COLIN |
| Final | 4/18/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Final | 4/18/2022 | Corrections Issued | AMY COLIN |
| HVAC-Final | 4/18/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 4/18/2022 | Corrections Issued | AMY COLIN |
| Service/Power Release | 4/18/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 4/18/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 4/20/2022 | Approved | AMY COLIN |
| Final | 4/20/2022 | Partial Inspection | AMY COLIN |
| HVAC-Final | 4/20/2022 | Approved | AMY COLIN |
| MERV13>=Final | 4/20/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 4/20/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Not Required | AMY COLIN |
| Service/Power Release | 4/20/2022 | Approved | AMY COLIN |
| Smoke Detectors | 4/20/2022 | Approved | AMY COLIN |
| Final | 2/2/2023 | OK to Issue CofO | AMY COLIN |