648-652 N NORTH SPRING ST 90012

Certificate Information: 648-652 N NORTH SPRING ST 90012

Application / Permit
20016-10000-07440
Plan Check / Job No.
B20LA05227
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
STRUCTRUAL UPGRADES, ADA BATHROOM UPGRADES, TENANT IMPROVEMENT IN (E)URM BUILDING.
Permit Issued
Issued on 6/5/2020
Issuing Office
Current Status
Permit Finaled on 12/1/2021

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/26/2020 SAMUEL GONZALEZ
Corrections Issued 4/10/2020 SAMUEL GONZALEZ
Quality Review Completed 4/14/2020 LAWRENCE QUIRANTE
Disabled Access Plans Picked Up 4/16/2020 APPLICANT
Building Plans Picked Up 4/17/2020 APPLICANT
Plan Check Approved 6/4/2020 SAMUEL GONZALEZ
Issued 6/5/2020 APPLICANT
Permit Finaled 11/30/2021 ERNESTO CORRAL

Permit Application Clearance Information

Sewer availability Cleared 4/28/2020 AVALYN KAMACHI
RDP Residential Hotel/SRO Cleared 5/7/2020 NICHOLAS KAWAZOE
Residential hotels Cleared 5/7/2020 NICHOLAS KAWAZOE
Redevelopment Project Area Cleared 5/29/2020 DAVID URITA
DAS Clearance Cleared 6/4/2020 SAMUEL GONZALEZ

Contact Information

Architect Mulcahy,, Kevin Patrick; Lic. No.: C31272 3048 N. COOLIDGE AVENUE      LOS ANGELES, CA 90039
Contractor Marcos Construction Inc; Lic. No.: 686859-B P O BOX 65552      LOS ANGELES, CA 90065
Engineer Smith,, Chris Wayne; Lic. No.: S6106 35 CATAMARAN ST      MARINA DEL REY, CA 90292

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/29/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 6/29/2020 Partial Approval DANIEL COLLINS
Deputy Steel/Welding 8/14/2020 Conditional Approval RONALD PACHECO
Footing/Foundation/Slab 8/14/2020 Partial Approval LANNY MERRICK
Reinforced Concrete Frame 8/14/2020 Partial Inspection LANNY MERRICK
Deputy Shotcrete 8/18/2020 Conditional Approval RONALD PACHECO
Footing/Foundation/Slab 9/15/2020 Partial Approval DANIEL COLLINS
Structural Steel Frame 9/15/2020 Partial Approval DANIEL COLLINS
Deputy Steel/Welding 10/6/2020 Conditional Approval RONALD PACHECO
Reinforced Concrete Frame 10/6/2020 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 11/12/2020 Conditional Approval RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Partial Approval DANIEL COLLINS
Structural Steel Frame 12/10/2020 Approved DANIEL COLLINS
Wall Anchors 12/10/2020 Approved DANIEL COLLINS
Wood Frame 12/10/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 1/21/2021 Partial Approval DANIEL COLLINS
Wood Frame 1/21/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 2/1/2021 Partial Approval DANIEL COLLINS
Wood Frame 2/1/2021 Partial Approval DANIEL COLLINS
Wood Frame 3/19/2021 Approved DANIEL COLLINS
Drywall Nailing 4/13/2021 Approved DANIEL COLLINS
Insulation 4/13/2021 Approved DANIEL COLLINS
Final 11/30/2021 Permit Finaled ERNESTO CORRAL
Reinforced Concrete Frame 11/30/2021 Approved ERNESTO CORRAL
Reinforced Masonry Frame 11/30/2021 Approved ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV No Gas ERNESTO CORRAL
Smoke Detectors 11/30/2021 Approved ERNESTO CORRAL