5422 N QUAKERTOWN AVE 91364
Certificate Information: 5422 N QUAKERTOWN AVE 91364
- Application / Permit
- 20016-10000-07374
- Plan Check / Job No.
- B20LA05189
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 8 STEEL SPECIAL CANTILEVER COLUMNS AND 2 SHEAR WALLS
- Permit Issued
- Issued on 10/26/2020
- Issuing Office
- Current Status
- CofC Issued on 3/17/2021
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2020 | JESSE VIDUYA |
| Corrections Issued | 3/23/2020 | JESSE VIDUYA |
| Quality Review Completed | 3/25/2020 | SAI KHUM |
| Building Plans Picked Up | 3/31/2020 | APPLICANT |
| Applicant returned to address corrections | 5/15/2020 | JESSE VIDUYA |
| Applicant returned to address corrections | 7/22/2020 | JESSE VIDUYA |
| Applicant returned to address corrections | 9/9/2020 | JESSE VIDUYA |
| Plan Check Approved | 9/10/2020 | JESSE VIDUYA |
| Issued | 10/26/2020 | APPLICANT |
| OK for CofC | 3/15/2021 | KENNETH ROBERTS |
| CofC Issued | 3/17/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/8/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Anchor Design & Build; Lic. No.: 1064763-B | 3106 E COLORADO BLVD #5818 PASADENA, CA 91117 |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: C84559 | 9163 LEROY STREET SAN GABRIEL, CA 91775 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2020 | Partial Inspection | DANIEL VARNUM |
| Wood Frame | 11/24/2020 | Partial Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 1/12/2021 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 1/26/2021 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 1/26/2021 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 2/4/2021 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 2/8/2021 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2021 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 2/16/2021 | Not Ready for Inspection | DANIEL VARNUM |
| Interior/Exterior Lathing | 2/17/2021 | Approved | DANIEL VARNUM |
| Final | 2/19/2021 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 2/19/2021 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 2/19/2021 | Approved | DANIEL VARNUM |
| Final | 3/15/2021 | OK for CofC | KENNETH ROBERTS |