2573 S BUNDY DR 90064
Certificate Information: 2573 S BUNDY DR 90064
- Application / Permit
- 20016-10000-07352
- Plan Check / Job No.
- B20LA05162
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE AND STORAGE TO ACCESSORY DWELLING UNIT. ALL WORK PER WFPP
- Permit Issued
- Issued on 10/7/2020
- Issuing Office
- Current Status
- CofO Issued on 8/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2020 | ADAM HEGAZI |
| Corrections Issued | 3/13/2020 | ADAM HEGAZI |
| Plan Check Approved | 9/29/2020 | GEORGE ALVAREZ |
| Issued | 10/7/2020 | APPLICANT |
| Building Plans Picked Up | 10/14/2020 | APPLICANT |
| CofO in Progress | 8/16/2023 | JESUS PINEDA |
| Permit Finaled | 8/16/2023 | DANIEL ORRANTE |
| CofO Issued | 8/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/13/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 3/13/2020 | ELENA LOPEZ |
| Construction near power lines | Cleared | 7/15/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/15/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/5/2022 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 12/5/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/8/2023 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 3/21/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 3/21/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/21/2023 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/21/2023 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/24/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 3/28/2023 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 5/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/16/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/16/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 6/16/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 6/16/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 6/16/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| Final | 8/7/2023 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 8/7/2023 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/7/2023 | SGSOV Not Ready | JESUS PINEDA |
| Final | 8/15/2023 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 8/15/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2023 | SGSOV Approved | JESUS PINEDA |