7000 W 3RD ST 90048

Certificate Information: 7000 W 3RD ST 90048

Application / Permit
20016-10000-07302
Plan Check / Job No.
B20LA05116
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Alteration to exterior stairway, ramp, elevated deck / entrance patio, handrails / guardrails and planters at front of (E) office building.
Permit Issued
Issued on 9/29/2020
Issuing Office
Current Status
Permit Finaled on 7/21/2021

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 HELEN NGUYEN
Corrections Issued 3/26/2020 HELEN NGUYEN
Quality Review Completed 4/2/2020 STANLEY RAAP
Disabled Access Plans Picked Up 4/23/2020 APPLICANT
Applicant returned to address corrections 7/16/2020 HELEN NGUYEN
Building Plans Picked Up 7/16/2020 APPLICANT
Green Plans Picked Up 9/23/2020 APPLICANT
Plan Check Approved 9/29/2020 HELEN NGUYEN
Issued 9/29/2020 APPLICANT
Permit Finaled 7/21/2021 JONATHAN QUACH

Permit Application Clearance Information

"D" conditions Cleared 6/1/2020 JOE LUCKEY
Green Code Cleared 6/15/2020 KHEDER ALRAZAA
DAS Clearance Cleared 9/3/2020 ELIZABETH TOMS

Contact Information

Architect Wilder,, Arthur J; Lic. No.: C27915 3859 CARDIFF AVENUE      CULVER CITY, CA 90232
Contractor L E Waters Construction Company; Lic. No.: 638709-B 6767 FOREST LAWN DR STE 300      LOS ANGELES, CA 90068
Engineer Garza,, Omar Leonel; Lic. No.: S5593 4215 TOLAND WAY      LOS ANGELES, CA 90065

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/4/2020 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 12/15/2020 Conditional Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 1/6/2021 Partial Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 1/7/2021 Conditional Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 2/3/2021 Approved TIMOTHY BUXTON
Final 6/22/2021 Not Ready for Inspection TIMOTHY BUXTON
Green Building Final 6/22/2021 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV No Gas TIMOTHY BUXTON
Smoke Detectors 6/22/2021 Approved TIMOTHY BUXTON
Final 7/21/2021 Permit Finaled JONATHAN QUACH