ADDITION/ REMODEL OF 2-STORY OFFICE BLDG: ADD (17'-10" X 30'-4") CANOPY W/ROOF DECK ON EASTSIDE. ADD 2-STORY (5' X 47'-5") ON NORTHSIDE. REMODEL INTERIOR/EXTERIOR, NEW PARTITIONS, RESTROOMS, FINISHES, RESTUCCO, WINDOWS. REPLACE (2) STAIRS. REPAVE PARKING LOT. ADD 1-VAN ACCESSIBLE AND 4-BICYCLE SPACES. ADD NEW ELEVATOR. ADD EQUIPMENT ROOFTOP PLATFORM.
Permit Issued
Issued on 5/3/2021
Issuing Office
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 JESSE JIMENEZ
Corrections Issued 3/26/2020 JESSE JIMENEZ
Quality Review Completed 4/1/2020 STANLEY RAAP
Disabled Access Plans Picked Up 4/17/2020 APPLICANT
Applicant returned to address corrections 9/28/2020 JESSE JIMENEZ
Green Plans Picked Up 1/12/2021 APPLICANT
Applicant returned to address corrections 2/3/2021 JESSE JIMENEZ
Applicant returned to address corrections 2/22/2021 JESSE JIMENEZ
Applicant returned to address corrections 3/3/2021 JESSE JIMENEZ
Applicant returned to address corrections 3/17/2021 JESSE JIMENEZ
Applicant returned to address corrections 4/22/2021 JESSE JIMENEZ
Plan Check Approved 4/26/2021 JESSE JIMENEZ
Issued 5/3/2021 APPLICANT
Building Plans Picked Up 5/4/2021 APPLICANT
CofO in Progress 8/5/2022 PAUL DAVIDSON
Permit Finaled 8/29/2022 DAVID TSAU
CofO Issued 8/29/2022 DAVID TSAU
Permit Finaled 8/29/2022 DAVID TSAU

Permit Application Clearance Information

Sewer availability Cleared 4/17/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/21/2020 DINAH GARIN
Highway dedication Cleared 8/27/2020 RAYMOND MUGAMBWA
"D" conditions Cleared 8/28/2020 TERRI OSBORNE
"Q" conditions Cleared 8/28/2020 TERRI OSBORNE
Low Impact Development Cleared 9/29/2020 JORGE MEJIA LEMUS
Permit Cleared 9/30/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 9/30/2020 DINAH GARIN
Green Code Cleared 11/5/2020 KHEDER ALRAZAA
DAS Clearance Cleared 1/5/2021 JESSE JIMENEZ
Grading Pre-Inspection Cleared 2/18/2021 JESSE JIMENEZ
GPI Written Notices Cleared 3/3/2021 JESSE JIMENEZ

Contact Information

Contractor Alonzo Construction Inc; Lic. No.: 485001-B 11556 BARMAN AVENUE      CULVER CITY, CA 90230
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803
Engineer Youngblood,, Charles St Denny; Lic. No.: C45031 556 SEGOVIA AVE      SAN GABRIEL, CA 91775

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/1/2021 Approved PAUL DAVIDSON
Footing/Foundation/Slab 6/16/2021 Partial Approval PAUL DAVIDSON
Wood Frame 6/16/2021 Corrections Issued PAUL DAVIDSON
Deputy Reinf. Concrete 6/17/2021 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 7/2/2021 Conditional Approval PAUL DAVIDSON
Footing/Foundation/Slab 7/2/2021 Partial Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 7/16/2021 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 7/20/2021 Partial Approval PAUL DAVIDSON
Deputy Steel/Welding 7/27/2021 Conditional Approval PAUL DAVIDSON
Footing/Foundation/Slab 7/28/2021 Approved PAUL DAVIDSON
Special/Order Compliance 8/24/2021 Partial Inspection PAUL DAVIDSON
Green Building Rough 8/31/2021 Approved PAUL DAVIDSON
Wood Frame 8/31/2021 Partial Approval PAUL DAVIDSON
Deputy Wood Construction 9/9/2021 Conditional Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Partial Approval PAUL DAVIDSON
Wood Frame 9/23/2021 Partial Approval PAUL DAVIDSON
Insulation 10/13/2021 Partial Approval PAUL DAVIDSON
Wood Frame 10/13/2021 Partial Approval PAUL DAVIDSON
Drywall Nailing 10/22/2021 Partial Approval PAUL DAVIDSON
Wood Frame 10/22/2021 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 10/26/2021 Partial Approval PAUL DAVIDSON
Wood Frame 11/5/2021 Partial Approval PAUL DAVIDSON
Wood Frame 11/10/2021 Not Ready for Inspection PAUL DAVIDSON
Pre-Inspection 11/15/2021 Partial Inspection PAUL DAVIDSON
Interior/Exterior Lathing 11/16/2021 Partial Approval PAUL DAVIDSON
Special/Order Compliance 11/16/2021 Corrections Issued PAUL DAVIDSON
Wood Frame 11/18/2021 Approved PAUL DAVIDSON
Insulation 11/22/2021 Approved PAUL DAVIDSON
Drywall Nailing 11/30/2021 Partial Approval PAUL DAVIDSON
Interior/Exterior Lathing 12/6/2021 Approved PAUL DAVIDSON
Drywall Nailing 12/10/2021 Partial Approval PAUL DAVIDSON
Wood Frame 1/11/2022 Partial Approval PAUL DAVIDSON
Drywall Nailing 1/28/2022 Partial Approval PAUL DAVIDSON
Drywall Nailing 2/1/2022 Partial Approval PAUL DAVIDSON
Pre-Inspection 2/1/2022 Partial Inspection PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 2/4/2022 Partial Approval PAUL DAVIDSON
Pre-Inspection 2/8/2022 Partial Inspection PAUL DAVIDSON
Reinforced Masonry Frame 2/10/2022 Partial Approval PAUL DAVIDSON
Pre-Inspection 3/2/2022 Partial Inspection PAUL DAVIDSON
Pre-Inspection 3/7/2022 Partial Approval PAUL DAVIDSON
Pre-Inspection 3/24/2022 Not Ready for Inspection JOHN DODGE
Footing/Foundation/Slab 3/29/2022 Partial Approval JOHN DODGE
Drywall Nailing 4/5/2022 Approved ALAN NOVAK
Final 7/22/2022 Partial Inspection PAUL DAVIDSON
Footing/Foundation/Slab 7/22/2022 Approved PAUL DAVIDSON
Green Building Final 7/22/2022 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 7/22/2022 Approved PAUL DAVIDSON
Wood Frame 7/22/2022 Approved PAUL DAVIDSON
Final 8/4/2022 OK to Issue CofO PAUL DAVIDSON