612 N SEPULVEDA BLVD 90049
Certificate Information: 612 N SEPULVEDA BLVD 90049
- Application / Permit
- 20016-10000-07263
- Plan Check / Job No.
- B20LA05101
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ADDITION/ REMODEL OF 2-STORY OFFICE BLDG: ADD (17'-10" X 30'-4") CANOPY W/ROOF DECK ON EASTSIDE. ADD 2-STORY (5' X 47'-5") ON NORTHSIDE. REMODEL INTERIOR/EXTERIOR, NEW PARTITIONS, RESTROOMS, FINISHES, RESTUCCO, WINDOWS. REPLACE (2) STAIRS. REPAVE PARKING LOT. ADD 1-VAN ACCESSIBLE AND 4-BICYCLE SPACES. ADD NEW ELEVATOR. ADD EQUIPMENT ROOFTOP PLATFORM.
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- CofO Issued on 8/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | JESSE JIMENEZ |
| Corrections Issued | 3/26/2020 | JESSE JIMENEZ |
| Quality Review Completed | 4/1/2020 | STANLEY RAAP |
| Disabled Access Plans Picked Up | 4/17/2020 | APPLICANT |
| Applicant returned to address corrections | 9/28/2020 | JESSE JIMENEZ |
| Green Plans Picked Up | 1/12/2021 | APPLICANT |
| Applicant returned to address corrections | 2/3/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 2/22/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 3/3/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 3/17/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 4/22/2021 | JESSE JIMENEZ |
| Plan Check Approved | 4/26/2021 | JESSE JIMENEZ |
| Issued | 5/3/2021 | APPLICANT |
| Building Plans Picked Up | 5/4/2021 | APPLICANT |
| CofO in Progress | 8/5/2022 | PAUL DAVIDSON |
| Permit Finaled | 8/29/2022 | DAVID TSAU |
| CofO Issued | 8/29/2022 | DAVID TSAU |
| Permit Finaled | 8/29/2022 | DAVID TSAU |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/17/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2020 | DINAH GARIN |
| Highway dedication | Cleared | 8/27/2020 | RAYMOND MUGAMBWA |
| "D" conditions | Cleared | 8/28/2020 | TERRI OSBORNE |
| "Q" conditions | Cleared | 8/28/2020 | TERRI OSBORNE |
| Low Impact Development | Cleared | 9/29/2020 | JORGE MEJIA LEMUS |
| Permit | Cleared | 9/30/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 9/30/2020 | DINAH GARIN |
| Green Code | Cleared | 11/5/2020 | KHEDER ALRAZAA |
| DAS Clearance | Cleared | 1/5/2021 | JESSE JIMENEZ |
| Grading Pre-Inspection | Cleared | 2/18/2021 | JESSE JIMENEZ |
| GPI Written Notices | Cleared | 3/3/2021 | JESSE JIMENEZ |
Contact Information
| Contractor | Alonzo Construction Inc; Lic. No.: 485001-B | 11556 BARMAN AVENUE CULVER CITY, CA 90230 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
| Engineer | Youngblood,, Charles St Denny; Lic. No.: C45031 | 556 SEGOVIA AVE SAN GABRIEL, CA 91775 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/1/2021 | Approved | PAUL DAVIDSON |
| Footing/Foundation/Slab | 6/16/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 6/16/2021 | Corrections Issued | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/17/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 7/2/2021 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/2/2021 | Partial Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/20/2021 | Partial Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 7/27/2021 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/28/2021 | Approved | PAUL DAVIDSON |
| Special/Order Compliance | 8/24/2021 | Partial Inspection | PAUL DAVIDSON |
| Green Building Rough | 8/31/2021 | Approved | PAUL DAVIDSON |
| Wood Frame | 8/31/2021 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 9/9/2021 | Conditional Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 9/23/2021 | Partial Approval | PAUL DAVIDSON |
| Insulation | 10/13/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 10/13/2021 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 10/22/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 10/22/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 10/26/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 11/5/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 11/10/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 11/15/2021 | Partial Inspection | PAUL DAVIDSON |
| Interior/Exterior Lathing | 11/16/2021 | Partial Approval | PAUL DAVIDSON |
| Special/Order Compliance | 11/16/2021 | Corrections Issued | PAUL DAVIDSON |
| Wood Frame | 11/18/2021 | Approved | PAUL DAVIDSON |
| Insulation | 11/22/2021 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 11/30/2021 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 12/6/2021 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 12/10/2021 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 1/11/2022 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 1/28/2022 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 2/1/2022 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 2/1/2022 | Partial Inspection | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 2/4/2022 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 2/8/2022 | Partial Inspection | PAUL DAVIDSON |
| Reinforced Masonry Frame | 2/10/2022 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 3/2/2022 | Partial Inspection | PAUL DAVIDSON |
| Pre-Inspection | 3/7/2022 | Partial Approval | PAUL DAVIDSON |
| Pre-Inspection | 3/24/2022 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 3/29/2022 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 4/5/2022 | Approved | ALAN NOVAK |
| Final | 7/22/2022 | Partial Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/22/2022 | Approved | PAUL DAVIDSON |
| Green Building Final | 7/22/2022 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 7/22/2022 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 7/22/2022 | Approved | PAUL DAVIDSON |
| Wood Frame | 7/22/2022 | Approved | PAUL DAVIDSON |
| Final | 8/4/2022 | OK to Issue CofO | PAUL DAVIDSON |