1724 S BARRY AVE 90025
Certificate Information: 1724 S BARRY AVE 90025
- Application / Permit
- 20016-10000-07190
- Plan Check / Job No.
- B20LA05034
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 3 SPECIAL STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 7/31/2020
- Issuing Office
- Current Status
- CofC Issued on 12/7/2020
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2020 | HANS SANTIAGO |
| Corrections Issued | 3/24/2020 | HANS SANTIAGO |
| Quality Review Completed | 3/27/2020 | SAI KHUM |
| Building Plans Picked Up | 3/31/2020 | APPLICANT |
| Applicant returned to address corrections | 4/27/2020 | HANS SANTIAGO |
| Plan Check Approved | 5/1/2020 | ANDREW SANTIAGO |
| Plan Check Approved | 7/20/2020 | ANDREW SANTIAGO |
| Issued | 7/31/2020 | APPLICANT |
| OK for CofC | 11/17/2020 | JOHN DODGE |
| CofC Issued | 12/7/2020 | TED RIES |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/10/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Sal Co Construction; Lic. No.: 779079-B | 2700 CAHUENGA BLVD # 1103 LOS ANGELES, CA 90068 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/20/2020 | Partial Approval | JOHN DODGE |
| Pre-Inspection | 8/21/2020 | Approved | JOHN DODGE |
| Deputy Reinf. Concrete | 9/11/2020 | Conditional Approval | JOHN DODGE |
| Deputy Steel/Welding | 9/15/2020 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 9/17/2020 | Not Ready for Inspection | JOHN DODGE |
| Structural Steel Frame | 9/17/2020 | Approved | JOHN DODGE |
| Footing/Foundation/Slab | 9/18/2020 | Approved | RUSSELL BONVOULOIR |
| Structural Steel Frame | 9/18/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 9/21/2020 | Conditional Approval | GRANT WOODS |
| Deputy Wood Construction | 10/8/2020 | Conditional Approval | GRANT WOODS |
| Wood Frame | 10/9/2020 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 10/16/2020 | Approved | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 10/21/2020 | Approved | RUSSELL BONVOULOIR |
| Final | 11/12/2020 | Conditional Approval | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Approved | JOHN DODGE |
| Smoke Detectors | 11/12/2020 | Approved | JOHN DODGE |
| Drywall Nailing | 11/13/2020 | Partial Inspection | RUSSELL BONVOULOIR |
| Final | 11/17/2020 | OK for CofC | JOHN DODGE |