126 S HOBART BLVD 90004

Certificate Information: 126 S HOBART BLVD 90004

Application / Permit
20016-10000-07137
Plan Check / Job No.
B20LA04966
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER STATE LAW.
Permit Issued
Issued on 2/4/2025
Issuing Office
Metro
Current Status
CofO Issued on 9/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 MONICA RAMIREZ
Corrections Issued 3/17/2020 MONICA RAMIREZ
Building Plans Picked Up 5/7/2020 APPLICANT
Plan Check Approved 9/28/2020 TSE MING HUANG
Plan Check Approved 9/28/2020 ADAM HEGAZI
Issued 2/4/2025 APPLICANT
CofO in Progress 9/19/2025 JEFFREY MEAD
Permit Finaled 9/20/2025 DEROLD HAUFF
CofO Issued 9/20/2025 DEROLD HAUFF
Permit Finaled 9/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/16/2020 JUAN ASHTON
Sewer availability Cleared 4/16/2020 JUAN ASHTON
Construction near power lines Cleared 9/18/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/22/2020 JUAN ASHTON

Contact Information

Architect Amador,, Lauren; Lic. No.: C37401 204 1/2 S. BERENDO ST.      LOS ANGELES, CA 90004
Contractor Owner-Builder       ,
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/14/2025 Corrections Issued JEFFREY MEAD
Underground Mechanical 4/14/2025 Approved JEFFREY MEAD
Sewer 5/8/2025 Approved JEFFREY MEAD
ELECTRICAL-Rough 5/15/2025 Corrections Issued JEFFREY MEAD
HVAC-Rough 5/15/2025 Approved JEFFREY MEAD
PLUMBING-Rough 5/15/2025 Approved JEFFREY MEAD
Wood Frame 5/15/2025 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 5/20/2025 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 5/20/2025 Approved JEFFREY MEAD
HVAC-Rough 5/20/2025 Approved JEFFREY MEAD
BUILDING-Rough-Frame 5/28/2025 Approved JEFFREY MEAD
Green Building Rough 5/28/2025 Approved JEFFREY MEAD
Insulation 5/28/2025 Corrections Issued JEFFREY MEAD
Insulation 6/2/2025 Approved JEFFREY MEAD
Shower Pan 6/2/2025 Approved JEFFREY MEAD
Drywall Nailing 6/6/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 6/6/2025 Partial Approval JEFFREY MEAD
ELECTRICAL-Final 8/15/2025 Approved JEFFREY MEAD
Final 8/15/2025 Corrections Issued JEFFREY MEAD
Green Building Final 8/15/2025 Not Ready for Inspection JEFFREY MEAD
HVAC-Final 8/15/2025 Approved JEFFREY MEAD
PLUMBING-Final 8/15/2025 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Not Required JEFFREY MEAD
Smoke Detectors 8/15/2025 Approved JEFFREY MEAD
Final 9/18/2025 OK to Issue CofO JEFFREY MEAD
Green Building Final 9/18/2025 Approved JEFFREY MEAD