865 S FIGUEROA ST 90017

Certificate Information: 865 S FIGUEROA ST 90017

Application / Permit
20016-10000-07048
Plan Check / Job No.
B20LA04886
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
NEW INTERCONNECTING STAIR BETWEEN 29TH AND 30TH FLOORS IN (E) OFFICE HIGHRISE BUILDING.
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
Issued on 7/7/2020

Permit Application Status History

Submitted 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 KEVIN MORALES
Corrections Issued 3/23/2020 KEVIN MORALES
Quality Review Completed 4/2/2020 YOUNG KIM
Building Plans Picked Up 4/10/2020 APPLICANT
Applicant returned to address corrections 5/29/2020 KEVIN MORALES
Plan Check Approved 7/7/2020 KEVIN MORALES
Issued 7/7/2020 APPLICANT

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 5/26/2020 MENOA AGHAJANI
DAS Clearance Cleared 6/25/2020 KEVIN MORALES

Contact Information

Contractor Environmental Contracting Corporation; Lic. No.: 491028-B 880 EAST 1ST STREET      LOS ANGELES, CA 90012
Engineer Graf,, Thomas Edward; Lic. No.: C34719 PO BOX 1105      TIBURON, CA 94920
Engineer Lam,, Howard Kam Ho; Lic. No.: S2717 32712 RACHEL CIRCLE      DANA POINT, CA 92629

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 8/4/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 8/6/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 8/7/2020 Conditional Approval KATY RAMIREZ
Insulation 8/12/2020 Approved JONATHAN QUACH
Structural Steel Frame 8/12/2020 Approved JONATHAN QUACH
Deputy Steel/Welding 8/13/2020 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 8/14/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 8/14/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 8/17/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 8/18/2020 Conditional Approval KATY RAMIREZ
Structural Steel Frame 8/18/2020 Partial Approval KATY RAMIREZ
Deputy Fireproofing 8/25/2020 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 8/25/2020 Partial Inspection KATY RAMIREZ
Structural Steel Frame 8/27/2020 Not Ready for Inspection KATY RAMIREZ
Structural Steel Frame 8/31/2020 Partial Inspection KATY RAMIREZ
Deputy Other (see comments) 9/1/2020 Conditional Approval KATY RAMIREZ
Deputy Fireproofing 9/8/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 9/17/2020 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 9/18/2020 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 9/21/2020 Partial Approval KATY RAMIREZ
Structural Steel Frame 9/21/2020 Partial Inspection KATY RAMIREZ
Deputy Fireproofing 9/22/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/23/2020 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 10/7/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 10/13/2020 Not Ready for Inspection DANIEL COLLINS
Final 10/21/2020 No Access for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 10/21/2020 No Access for Inspection KATY RAMIREZ
Final 10/29/2020 Not Ready for Inspection KATY RAMIREZ
Smoke Detectors 10/29/2020 Approved KATY RAMIREZ