4255-4255 1/2 E SAN RAFAEL AVE 90065
Certificate Information: 4255-4255 1/2 E SAN RAFAEL AVE 90065
- Application / Permit
- 20016-10000-06960
- Plan Check / Job No.
- B20LA04802
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 9/8/2020
- Issuing Office
- Current Status
- CofO Issued on 3/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2020 | KEVIN MORALES |
| Corrections Issued | 3/10/2020 | KEVIN MORALES |
| Plan Check Approved | 6/1/2020 | FERNANDO FLORES |
| Issued | 9/8/2020 | APPLICANT |
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| CofO in Progress | 3/15/2021 | OSVALDO PARAMO |
| CofO in Progress | 3/15/2021 | OSVALDO PARAMO |
| CofO in Progress | 3/15/2021 | OSVALDO PARAMO |
| Permit Finaled | 3/24/2021 | DEROLD HAUFF |
| CofO Issued | 3/24/2021 | DEROLD HAUFF |
| Permit Finaled | 3/24/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | ELENA LOPEZ |
| Grading Pre-Inspection | Cleared | 3/10/2020 | KEVIN MORALES |
| Sewer availability | Cleared | 3/10/2020 | ELENA LOPEZ |
| Specific Plan | Cleared | 5/12/2020 | NASHYA JENSEN |
Contact Information
| Architect | Williams,, Pavlina; Lic. No.: C29593 | 2812 3RD AVE. LOS ANGELES, CA 90018 |
| Contractor | Refinish Plus Inc; Lic. No.: 1050293-B | 8133 PURITAN ST DOWNEY, CA 90242 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/22/2020 | Approved | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 10/15/2020 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 10/15/2020 | Approved | OSVALDO PARAMO |
| Sewer | 10/15/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/2/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 11/2/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 11/2/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/6/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 11/6/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 11/6/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/14/2020 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 11/14/2020 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 11/14/2020 | Approved | SCOTT FINNILA |
| Wood Frame | 11/14/2020 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/23/2020 | Approved | COREY HUPP |
| Wood Frame | 11/23/2020 | Not Ready for Inspection | COREY HUPP |
| Gas Test | 12/8/2020 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 12/8/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 12/8/2020 | Approved | OSVALDO PARAMO |
| Insulation | 12/14/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 12/14/2020 | Partial Inspection | OSVALDO PARAMO |
| Drywall Nailing | 12/16/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 1/6/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/5/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 2/5/2021 | Approved | OSVALDO PARAMO |
| Final | 2/5/2021 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 2/5/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 2/5/2021 | Approved | OSVALDO PARAMO |
| Final | 2/9/2021 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/9/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 2/9/2021 | Approved | OSVALDO PARAMO |