15089-15091 W NURMI ST 91342

Certificate Information: 15089-15091 W NURMI ST 91342

Application / Permit
20016-10000-06952
Plan Check / Job No.
B20LA04790
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 5/20/2020
Issuing Office
Current Status
CofO Issued on 10/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2020 APPLICANT
Assigned to Plan Check Engineer 3/10/2020 KEVIN MORALES
Corrections Issued 3/10/2020 KEVIN MORALES
Plan Check Approved 4/24/2020 RAHEL BEYENE
No Progress 4/24/2020 RAHEL BEYENE
Plan Check Approved 4/24/2020 RAHEL BEYENE
Building Plans Picked Up 4/30/2020 APPLICANT
Issued 5/20/2020 APPLICANT
CofO in Progress 9/12/2020 MISAEL ESPARZA
CofO Issued 10/19/2020 MICHAEL SMITH
Permit Finaled 10/19/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/13/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/13/2020 ELENA LOPEZ
Sewer availability Cleared 3/13/2020 ELENA LOPEZ
Grading Pre-Inspection Cleared 3/16/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/3/2020 Approved TROY SANDERS
ELECTRICAL-Rough 6/3/2020 Approved TROY SANDERS
Footing/Foundation/Slab 6/3/2020 Approved TROY SANDERS
Green Building Rough 6/3/2020 Approved TROY SANDERS
HVAC-Rough 6/3/2020 Approved TROY SANDERS
PLUMBING-Rough 6/3/2020 Approved TROY SANDERS
Drywall Nailing 7/15/2020 Approved GREGG CUMMINGS
Final 7/15/2020 Corrections Issued GREGG CUMMINGS
Insulation 7/15/2020 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/15/2020 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 7/15/2020 Approved GREGG CUMMINGS
Final 7/17/2020 Corrections Issued GREGG CUMMINGS
Final 8/12/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 9/11/2020 Approved MISAEL ESPARZA
Final 9/11/2020 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 9/11/2020 Approved MISAEL ESPARZA
PLUMBING-Final 9/11/2020 Approved MISAEL ESPARZA