5333 N RIVERTON AVE 91601
Certificate Information: 5333 N RIVERTON AVE 91601
- Application / Permit
- 20016-10000-06946
- Plan Check / Job No.
- B20LA04785
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMNS AND PLYWOOD SHEAR WALLS.
- Permit Issued
- Issued on 6/30/2020
- Issuing Office
- Current Status
- CofC Issued on 10/7/2021
Permit Application Status History
| Submitted | 3/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2020 | MANUEL MONTUFAR |
| Corrections Issued | 4/7/2020 | MANUEL MONTUFAR |
| Quality Review Completed | 4/14/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 5/8/2020 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 5/22/2020 | MANUEL MONTUFAR |
| Plan Check Approved | 5/28/2020 | MANUEL MONTUFAR |
| Issued | 6/30/2020 | APPLICANT |
| OK for CofC | 7/2/2021 | KENNETH ROBERTS |
| CofC Issued | 10/7/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 5/11/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 5/14/2020 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 6/24/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Repipe 1 Restoration Inc; Lic. No.: 1003868-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 8/21/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 8/24/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 8/24/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/24/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 9/4/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/4/2020 | Partial Approval | JOE VELASQUEZ |
| Structural Steel Frame | 9/18/2020 | Approved | JOE VELASQUEZ |
| Wood Frame | 9/18/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 9/24/2020 | Approved | JOE VELASQUEZ |
| Final | 6/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| METHANE-Final | 6/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/14/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 6/14/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 7/2/2021 | OK for CofC | KENNETH ROBERTS |
| METHANE-Final | 7/2/2021 | Approved | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 7/2/2021 | Approved | KENNETH ROBERTS |