700 W 7TH ST 90017
Certificate Information: 700 W 7TH ST 90017
- Application / Permit
- 20016-10000-06939
- Plan Check / Job No.
- B20LA04779
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- FULL-FLOOR TENANT IMPROVEMENT ON 33RD FLOOR. NEW PARTITIONS, CEILINGS, AND FINISHES.
- Permit Issued
- Issued on 6/18/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/5/2021
Permit Application Status History
| Submitted | 3/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | KEVIN MORALES |
| Corrections Issued | 3/17/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 5/21/2020 | SHANGQIN XIE |
| Plan Check Approved | 6/4/2020 | KEVIN MORALES |
| Issued | 6/18/2020 | LADBS |
| Building Plans Picked Up | 6/18/2020 | APPLICANT |
| Permit Finaled | 1/4/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| Fire Marshall Fire Life Safety | Cleared | 5/13/2020 | MENOA AGHAJANI |
Contact Information
| Architect | Swartz,, David Louis; Lic. No.: C19729 | 1437 4TH STREET SUITE 400 SANTA MONICA, CA 90401 |
| Contractor | Howard Building Corporation; Lic. No.: 445804-B | 707 WILSHIRE BLVD STE 3750 LOS ANGELES, CA 90017 |
| Engineer | Hershberg,, Mark Aaron; Lic. No.: S5078 | 6080 CENTER DR STE 300 LOS ANGELES, CA 90045 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 7/14/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 7/14/2020 | Corrections Issued | DANIEL COLLINS |
| Light Gage Steel Frame | 7/28/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 8/11/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 8/12/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 8/14/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 8/19/2020 | Conditional Approval | DANIEL COLLINS |
| Structural Steel Frame | 8/24/2020 | Partial Inspection | DANIEL COLLINS |
| Light Gage Steel Frame | 9/18/2020 | Partial Inspection | KATY RAMIREZ |
| T-Bar Ceiling | 9/18/2020 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 9/23/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 9/25/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 9/29/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 10/22/2020 | Approved | DANIEL COLLINS |
| T-Bar Ceiling | 10/22/2020 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 10/30/2020 | Approved | DANIEL COLLINS |
| Light Gage Steel Frame | 10/30/2020 | Approved | DANIEL COLLINS |
| Pre-Inspection | 11/10/2020 | Approved | DANIEL COLLINS |
| Final | 11/18/2020 | Corrections Issued | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 11/18/2020 | Approved | DANIEL COLLINS |
| Final | 12/23/2020 | Conditional Approval | DANIEL COLLINS |
| Final | 1/4/2021 | Permit Finaled | DANIEL COLLINS |