748 N HUDSON AVE 90038
Certificate Information: 748 N HUDSON AVE 90038
- Application / Permit
- 20016-10000-06591
- Plan Check / Job No.
- B20LA04519
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 1 NEW STEEL SPECIAL CANTILEVER COLUMN AND (2) ODRINARY MOMENT FRAME.
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/5/2022
Permit Application Status History
| Submitted | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | JESSE VIDUYA |
| Corrections Issued | 3/23/2020 | JESSE VIDUYA |
| Quality Review Completed | 3/27/2020 | SAI KHUM |
| Applicant returned to address corrections | 7/15/2020 | JESSE VIDUYA |
| Plan Check Approved | 9/16/2020 | JESSE VIDUYA |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| Issued | 5/16/2022 | APPLICANT |
| OK for CofC | 12/2/2022 | WINSTON DUNNING |
| CofC Issued | 12/5/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/19/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Muller Ariel; Lic. No.: 1026822-B | 525 N FULLER AVE LOS ANGELES, CA 90036 |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/23/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 6/17/2022 | Conditional Approval | BRUCE CAMPBELL |
| Excavation/Setback/Form/Re-Bar | 6/17/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 6/17/2022 | Partial Approval | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 6/22/2022 | Not Ready for Inspection | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 6/24/2022 | Approved | BRUCE CAMPBELL |
| Final | 8/24/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 8/24/2022 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/24/2022 | Approved | DARRYL ARNOLD |
| Final | 12/2/2022 | OK for CofC | WINSTON DUNNING |