860 S WESTCHESTER PL 90005
Certificate Information: 860 S WESTCHESTER PL 90005
- Application / Permit
- 20016-10000-06548
- Plan Check / Job No.
- B20LA04462
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) 2-story rec. rom into an ADU with addition for egress. "Convert existing accessory building to detached ADU per state law GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 10/29/2020
- Issuing Office
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2020 | HELEN NGUYEN |
| Corrections Issued | 4/6/2020 | HELEN NGUYEN |
| Quality Review Completed | 4/13/2020 | STANLEY RAAP |
| Green Plans Picked Up | 9/1/2020 | APPLICANT |
| Plan Check Approved | 10/8/2020 | HELEN NGUYEN |
| Issued | 10/29/2020 | APPLICANT |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| CofO in Progress | 4/11/2022 | CRAIG DAVIS |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
| CofO Issued | 4/13/2022 | DEROLD HAUFF |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 7/14/2020 | ELENA LOPEZ |
| CPC | Cleared | 8/10/2020 | AMANDA KAINER |
| HPOZ | Cleared | 8/10/2020 | AMANDA KAINER |
| Miscellaneous | Cleared | 8/10/2020 | AMANDA KAINER |
| Miscellaneous | Cleared | 8/10/2020 | AMANDA KAINER |
| Miscellaneous | Cleared | 8/10/2020 | AMANDA KAINER |
| Green Code | Cleared | 9/1/2020 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 10/26/2020 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/15/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 4/17/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/23/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 4/23/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/29/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/13/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/13/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/13/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 5/13/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/13/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/21/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/21/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 5/28/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Final | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/28/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 4/8/2022 | OK to Issue CofO | CRAIG DAVIS |