930 S HILGARD AVE 90024
Certificate Information: 930 S HILGARD AVE 90024
- Application / Permit
- 20016-10000-06545
- Plan Check / Job No.
- B20LA04455
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- VOLUNTARY TI - REMOVE EXISTING BATHTUBS, REPLACE WITH SHOWERS IN 160 SPECIFIC GUEST ROOMS.
- Permit Issued
- Issued on 6/18/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/3/2020
Permit Application Status History
| Submitted | 3/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2020 | FARSHAD ALIMOHAMADI |
| Disabled Access Plans Picked Up | 4/30/2020 | APPLICANT |
| Corrections Issued | 6/1/2020 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 6/1/2020 | CHIHARU SUZUKI |
| Plan Check Approved | 6/1/2020 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 6/1/2020 | APPLICANT |
| Issued | 6/18/2020 | LADBS |
| Permit Finaled | 9/2/2020 | PAUL DAVIDSON |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/1/2020 | RONALD ALLEN |
Contact Information
| Contractor | Award Construction And Restoration Inc; Lic. No.: 922754-B | 2361 HOGAN LN LAKE HAVASU CITY, AZ 86406 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 6/26/2020 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 7/2/2020 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/8/2020 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/15/2020 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/20/2020 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/22/2020 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/24/2020 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/30/2020 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/31/2020 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 8/6/2020 | Approved | PAUL DAVIDSON |
| Final | 9/2/2020 | Permit Finaled | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 9/2/2020 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 9/2/2020 | Approved | PAUL DAVIDSON |