3800 S VERMONT AVE 90037

Certificate Information: 3800 S VERMONT AVE 90037

Application / Permit
20016-10000-06388
Plan Check / Job No.
B20LA04321
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Museum non-profit
Work Description
SUPPLEMENTAL TO 17010-10000-01465 DEFERRED SUBMITTAL FOR SECONDARY FRAMING SYSTEM SUPPORTING EXTERIOR FACADE OF NEW MUSEUM (SEQUENCE B)
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
Permit Finaled on 11/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 PRANITA SHAH
Corrections Issued 4/1/2020 PRANITA SHAH
Quality Review Completed 4/2/2020 MINYE PAK
Applicant returned to address corrections 4/17/2020 PRANITA SHAH
Applicant returned to address corrections 5/7/2020 PRANITA SHAH
Applicant returned to address corrections 8/25/2020 PRANITA SHAH
Applicant returned to address corrections 8/27/2020 PRANITA SHAH
Applicant returned to address corrections 9/11/2020 PRANITA SHAH
Plan Check Approved 9/24/2020 PRANITA SHAH
Issued 9/24/2020 APPLICANT
Permit Finaled 11/3/2023 JAMES POWERS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Martin Bros/Marcowall Inc; Lic. No.: 246274-B P O BOX 2089      GARDENA, CA 90247

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/10/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/17/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/18/2020 Not Ready for Inspection LANNY MERRICK
Light Gage Steel Frame 12/21/2020 Partial Approval JAMES POWERS
Drywall Nailing 1/13/2021 Partial Approval JAMES POWERS
Insulation 1/21/2021 Not Ready for Inspection LANNY MERRICK
Insulation 1/22/2021 Partial Inspection JAMES POWERS
Light Gage Steel Frame 1/22/2021 Partial Approval JAMES POWERS
Insulation 1/26/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/26/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/5/2021 Partial Approval JAMES POWERS
Drywall Nailing 2/17/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/24/2021 Partial Approval JAMES POWERS
Drywall Nailing 3/31/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/4/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/19/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/30/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/9/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/2/2021 Partial Approval JAMES POWERS
Insulation 9/8/2021 Partial Approval JAMES POWERS
Insulation 9/10/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/10/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/24/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/1/2021 Partial Approval TED RIES
Light Gage Steel Frame 3/29/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 3/31/2022 Partial Approval BRUCE CAMPBELL
Light Gage Steel Frame 5/25/2022 Partial Inspection RUSSELL BONVOULOIR
Light Gage Steel Frame 5/26/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 5/27/2022 Partial Inspection RUSSELL BONVOULOIR
Insulation 6/6/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 6/6/2022 Partial Approval RUSSELL BONVOULOIR
Insulation 6/13/2022 Partial Approval RUSSELL BONVOULOIR
Interior/Exterior Lathing 6/13/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 6/13/2022 Partial Approval RUSSELL BONVOULOIR
Insulation 6/14/2022 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 6/14/2022 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 6/16/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/16/2022 Partial Approval JAMES POWERS
Insulation 6/22/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 6/22/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 6/24/2022 Conditional Approval GREGORY POMISH
Light Gage Steel Frame 6/29/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 7/7/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 7/11/2022 Partial Approval DAVID BURKHEAD
Insulation 7/18/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 7/18/2022 Partial Approval RUSSELL BONVOULOIR
Insulation 7/22/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 7/22/2022 Not Ready for Inspection JAMES POWERS
Insulation 7/25/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 7/25/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 8/4/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 8/23/2022 Partial Approval TIMOTHY BUXTON
Insulation 9/15/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 9/15/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 9/19/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 12/9/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/22/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 12/27/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/29/2022 Partial Approval JAMES POWERS
Insulation 1/17/2023 Partial Approval ALFREDO LOPEZ
Structural Steel Frame 1/17/2023 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 2/1/2023 Partial Approval JAMES POWERS
Insulation 2/6/2023 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 2/6/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/14/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/28/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/7/2023 Partial Approval KATY RAMIREZ
Interior/Exterior Lathing 4/5/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/10/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/16/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/26/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/26/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/6/2023 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 6/8/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/21/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/27/2023 Partial Approval ALAN MORELOS
Light Gage Steel Frame 8/3/2023 Partial Approval ALAN MORELOS
Light Gage Steel Frame 9/13/2023 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 10/16/2023 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/27/2023 Partial Approval LARRY ARNICK
Final 11/3/2023 Permit Finaled JAMES POWERS