1325 N WESTERN AVE 90027

Certificate Information: 1325 N WESTERN AVE 90027

Application / Permit
20016-10000-06308
Plan Check / Job No.
B20LA04270
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Homeless Shelter
Work Description
TENANT IMPROVEMENTS TO EXISTING TRANSITIONAL LIVING CENTER. INCREASE BED COUNT TO 86 TOTAL BEDS. NO ADDITION OF NEW FLOOR AREA.
Permit Issued
Issued on 10/27/2020
Issuing Office
Metro
Current Status
CofO Corrected on 11/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 EUGENE BARBEAU
Corrections Issued 3/10/2020 EUGENE BARBEAU
Disabled Access Plans Picked Up 3/10/2020 APPLICANT
Quality Review Completed 3/11/2020 PETER KIM
Green Plans Picked Up 3/11/2020 APPLICANT
Plan Check Approved 10/20/2020 EUGENE BARBEAU
Issued 10/27/2020 APPLICANT
Building Plans Picked Up 10/27/2020 APPLICANT
CofO in Progress 7/15/2021 RUSSELL BONVOULOIR
CofO Issued-Status Void 7/20/2021 ERNESTO CORRAL
Permit Finaled-Status Void 7/20/2021 ERNESTO CORRAL
Re-Activate Permit 11/8/2022 ERNESTO CORRAL
Permit Finaled 11/10/2022 ERNESTO CORRAL
CofO Corrected 11/10/2022 ERNESTO CORRAL
Permit Finaled 11/10/2022 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/22/2020 WALLIE JONG
Sewer availability Cleared 5/22/2020 WALLIE JONG
ZA Case Cleared 6/5/2020 RUBEN VASQUEZ
DAS Clearance Cleared 6/19/2020 EUGENE BARBEAU
Redevelopment Project Area Cleared 7/14/2020 DAVID URITA
Fire Marshall Fire Life Safety Cleared 10/8/2020 MENOA AGHAJANI
Green Code Cleared 10/18/2020 DONALD CRICHLOW

Contact Information

Architect Debbas,, Charles George; Lic. No.: C23875 2550 NINTH STREET SUITE 210B      BERKELEY, CA 94710
Contractor Anvil Construction Company Inc; Lic. No.: 998987-B 8895 RESEARCH DRIVE      IRVINE, CA 92618

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2020 Approved RUSSELL BONVOULOIR
Light Gage Steel Frame 11/25/2020 Approved RUSSELL BONVOULOIR
Drywall Nailing 3/24/2021 Partial Approval TIMOTHY BUXTON
Green Building Rough 3/24/2021 Approved TIMOTHY BUXTON
Drywall Nailing 3/31/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 4/6/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Drywall Nailing 4/12/2021 Approved RUSSELL BONVOULOIR
Partition/T-Bar Ceiling 4/27/2021 Not Ready for Inspection TIMOTHY BUXTON
Partition/T-Bar Ceiling 5/5/2021 Partial Approval RUSSELL BONVOULOIR
Interior/Exterior Lathing 5/14/2021 Approved RUSSELL BONVOULOIR
Partition/T-Bar Ceiling 5/14/2021 Approved RUSSELL BONVOULOIR
Light Gage Steel Frame 5/24/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 5/27/2021 Approved RUSSELL BONVOULOIR
Pre-Inspection 6/10/2021 Approved RUSSELL BONVOULOIR
Deputy Steel/Welding 7/7/2021 Conditional Approval RUSSELL BONVOULOIR
Green Building Final 7/7/2021 Approved RUSSELL BONVOULOIR
Pre-Inspection 7/7/2021 Approved RUSSELL BONVOULOIR
Final 7/9/2021 Conditional Approval RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Approved RUSSELL BONVOULOIR
Smoke Detectors 7/9/2021 Approved RUSSELL BONVOULOIR
Wood Frame 7/9/2021 Approved RUSSELL BONVOULOIR
Final 7/14/2021 Conditional Approval RUSSELL BONVOULOIR