729 N SEWARD ST 90038
Certificate Information: 729 N SEWARD ST 90038
- Application / Permit
- 20016-10000-06182
- Plan Check / Job No.
- B20LA04180
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT TO 3 FLOORS (BASEMENT, 1ST FLOOR, 2ND FLOOR) WITHIN EXISTING OFFICE BUILDING INCLUDING NEW PARTITIONS, DOORS, CEILING, LIGHTING, AND FINISHES.
- Permit Issued
- Issued on 7/7/2020
- Issuing Office
- Current Status
- Permit Finaled on 2/9/2021
Permit Application Status History
| Submitted | 3/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | LAMAR DAVIS |
| Corrections Issued | 3/23/2020 | LAMAR DAVIS |
| Disabled Access Plans Picked Up | 3/26/2020 | APPLICANT |
| Quality Review Completed | 4/15/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 4/17/2020 | APPLICANT |
| Green Plans Picked Up | 6/24/2020 | APPLICANT |
| Plan Check Approved | 7/2/2020 | LAMAR DAVIS |
| Issued | 7/7/2020 | APPLICANT |
| Permit Finaled | 2/8/2021 | TIMOTHY BUXTON |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/7/2020 | ELIZABETH TOMS |
| Green Code | Cleared | 6/22/2020 | KHEDER ALRAZAA |
Contact Information
| Architect | Kamus,, John Howard; Lic. No.: C20397 | 5364 EVENING SKY DRIVE SIMI VALLEY, CA 93063 |
| Contractor | Gray West Construction Inc; Lic. No.: 775947-B | 421 E CERRITOS AVENUE ANAHEIM, CA 92805 |
| Engineer | Bryson,, Michael Butler; Lic. No.: S4979 | 285 W 6TH ST 508 SAN PEDRO, CA 90731 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2020 | Approved | JONATHAN QUACH |
| Deputy Other (see comments) | 8/31/2020 | Conditional Approval | TIMOTHY BUXTON |
| Wood Frame | 9/4/2020 | Partial Approval | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 9/8/2020 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 9/8/2020 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 9/9/2020 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 9/15/2020 | Partial Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 9/16/2020 | Partial Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 9/17/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Light Gage Steel Frame | 9/18/2020 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 9/18/2020 | Partial Approval | JONATHAN QUACH |
| Insulation | 9/28/2020 | Approved | JONATHAN QUACH |
| Wood Frame | 9/28/2020 | Approved | JONATHAN QUACH |
| Drywall Nailing | 10/5/2020 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 10/9/2020 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 10/9/2020 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 10/19/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Drywall Nailing | 10/21/2020 | Partial Inspection | TIMOTHY BUXTON |
| Wood Frame | 10/21/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 11/2/2020 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 12/7/2020 | Approved | JONATHAN QUACH |
| Final | 12/16/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 12/16/2020 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 12/16/2020 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 12/16/2020 | Approved | TIMOTHY BUXTON |
| Final | 12/23/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 1/27/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 1/27/2021 | Approved | TIMOTHY BUXTON |
| Final | 2/5/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 2/8/2021 | Permit Finaled | TIMOTHY BUXTON |