4011 1/2 W 60TH ST 90043
Certificate Information: 4011 1/2 W 60TH ST 90043
- Application / Permit
- 20016-10000-06136
- Plan Check / Job No.
- B20LA04151
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 16'X18' GARAGE TO ACCESSORY DWELLING UNIT PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofO Issued on 2/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2020 | GEORGE ALVAREZ |
| Corrections Issued | 3/2/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 5/7/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 6/8/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/30/2020 | JESSE JIMENEZ |
| Plan Check Approved | 7/6/2020 | JESSE JIMENEZ |
| Building Plans Picked Up | 7/8/2020 | APPLICANT |
| Issued | 7/17/2020 | APPLICANT |
| CofO in Progress | 9/9/2021 | FREDDIE RIVERA |
| Permit Finaled | 2/24/2023 | DANIEL ORRANTE |
| CofO Issued | 2/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2020 | THOMAS LANG |
| Address approval | Cleared | 3/5/2020 | THOMAS LANG |
| Sewer availability | Cleared | 4/8/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2020 | JUAN ASHTON |
| Construction near power lines | Cleared | 5/13/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 5/13/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/5/2021 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 1/8/2021 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/8/2021 | Partial Approval | FREDDIE RIVERA |
| Sewer | 1/8/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/15/2021 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 1/15/2021 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/25/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 2/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 2/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/19/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/23/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/23/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/23/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 4/23/2021 | Conditional Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/23/2021 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 4/23/2021 | Approved | FREDDIE RIVERA |
| Insulation | 5/10/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/10/2021 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 5/18/2021 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/27/2021 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 8/23/2021 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 8/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 8/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Final | 8/23/2021 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Final | 8/23/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 8/23/2021 | Partial Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/23/2021 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 8/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 8/26/2021 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 8/26/2021 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 8/26/2021 | Approved | FREDDIE RIVERA |